Sovereign Network Group (202451134)
|
Decision |
|
|
Case ID |
202451134 |
|
Decision type |
Investigation |
|
Landlord |
Sovereign Network Group |
|
Landlord type |
Housing Association |
|
Occupancy |
Shared Ownership |
|
Date |
27 October 2025 |
Background
- The resident lives in a 2-bedroom house. She told the landlord that she has a diagnosis of asthma.
What the complaint is about
- The complaint is about the landlord’s handling of:
a) A roof leak and associated damp.
b) Reports about staff conduct.
c) The complaint.
Our decision (determination)
- We have found that:
a) There was reasonable redress in the landlord’s response to the roof leak and associated damp.
b) There was service failure in the landlord’s handling of staff conduct.
c) There was service failure in the landlord’s handling of the complaint.
We have made orders for the landlord to put things right.
Summary of reasons
Roof leak
- The landlord did not have responsibility to repair the roof and the associated damp issues. However, it decided to do so and took 3 months to complete the repair. This meant that it incurred costs that would reasonably have been the responsibility of the resident. We therefore consider that it has provided reasonable redress for the time, trouble, distress, and inconvenience its miscommunication caused.
Staff conduct
- The landlord apologised for the conduct of the staff member and said that it would investigate this. It also offered £50 compensation. However, we have seen no evidence of the investigation it took regarding the matter.
Complaint
- There were delays in acknowledging the stage 1 complaint and providing a stage 2 complaint response.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order
The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:
|
No later than 24 November 2025 |
|
2 |
Compensation order The landlord must pay the resident £200 made up as follows:
This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date. The landlord may deduct from the total figure the £100 it has already paid regarding these complaint points.
|
No later than 24 November 2025 |
|
3 |
A manager must carry out an independent review of this case to understand and explain why the failings occurred and consider if they were limited to this case. A report should be provided to us regarding the findings within 12 weeks of the date of this report. The review should include the following and provide a timed implementation plan for any identified improvements:
|
No later than 19 January 2026 |
Recommendations
Our recommendations are not binding, and a landlord may decide not to follow them.
|
Our recommendations |
|
The resident advised us in October 2025 that staining has returned to the previously treated area. She said that the landlord told her when it completed the work initially that she should contact it again if this happened. This means that she is still uncertain about the landlord’s and her responsibilities regarding repairs. The landlord must therefore contact her to discuss this and put in writing its position regarding such repairs moving forward. |
Our investigation
The complaint procedure
|
Date |
What happened |
|
4 February 2025 |
The resident raised her complaint about the handling of the repair to the roof and the landlord’s lack of communication. She said that:
caused by the leak.
a door, got mud on her bedding, and a curtain tie was missing.
|
|
26 February 2025 |
The landlord acknowledged receipt of the complaint. |
|
11 March 2025 |
The landlord provided a stage 1 complaint response. It said that:
of the property. However, it had completed the work as a gesture of goodwill.
issues with this.
to the property and offered her £25 for the inconvenience caused.
damp and mould on 15 April 2025. |
|
18 March 2025 |
The resident asked the landlord to escalate the complaint to stage 2 of the complaints process because she was unhappy with the level of compensation offered and the stage 1 decision. |
|
24 April 2025 |
The landlord provided a stage 2 complaint response. It said that:
|
|
Referral to the Ombudsman |
The resident remained dissatisfied with the outcome and contacted us. She felt that the landlord had not adequately compensated her considering that she had been unable to use the bedroom. |
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
Roof leak and associated damp |
|
Finding |
Reasonable redress |
- The lease confirms that the resident is responsible for keeping the property in good repair.
- The resident told the landlord that the roof was leaking on 27 November 2024.
- The landlord inspected the property and decided that there was a leak from the dummy chimney on the roof. It raised repairs jobs to rectify the issue and missed an appointment which cost the resident time and trouble. It considered taking the dummy chimney off, however, found that it could not do so because the property was in a conservation area.
- There were delays in erecting scaffolding and the resident took time and trouble contacting the landlord on several occasions to chase this up.
- It took approximately 3 months for the landlord to rectify the source of the leak during which time the resident was living with damp in the bedrooms which meant that she had to sleep in the living room. This caused her distress and inconvenience which was particularly distressing as she is diagnosed with asthma.
- The landlord was not responsible for completing the repairs but we have seen no evidence that it told the resident this until the stage 1 complaint response. Had it been clear from the outset she might have arranged her own contractors to carry out the work. However, this would have incurred a considerable monetary cost which the landlord took on instead.
- Overall, considering that the landlord also repainted the affected area and fitted a new extractor fan in the bathroom we consider that it has given reasonable redress to the resident. This counteracts its miscommunication about whose responsibility the repair was and the time, trouble, distress, and inconvenience this caused her.
|
Complaint |
Staff conduct |
|
Finding |
Service failure |
- On 31 January 2025 the resident told the landlord that an operative had caused damage to her property while treating the damp and mould. We will not form a view on whether the staff member’s actions themselves were appropriate. Our role is to decide whether the landlord investigated and responded to the complaint, and took proportionate action based on the information available. For example, the landlord would generally be expected to conduct interviews and gather evidence from both parties, making an informed decision based on its findings.
- In the stage 2 complaint response the landlord apologised to the resident. It said that it would deal with the matter internally and offered £50 compensation. It was appropriate for it to not divulge any details about the conversations it had with the staff member.
- The landlord said that it had passed the resident’s concerns onto a manager to deal with internally. However, we have seen no evidence or notes taken regarding any interviews with the staff member and the outcome of this. Therefore, there was service failure in its handling of the residents concerns about staff conduct.
|
Complaint |
The handling of the complaint |
|
Finding |
Service failure |
- The Housing Ombudsman’s complaint handling code (the Code) says that stage 1 complaints should be acknowledged within 5 working days of being received.
- In this case the landlord took 26 working days to log and acknowledge the complaint. This prolonged the complaints process which meant that the resident was waiting longer for a resolution which caused her distress.
- The landlord’s complaint policy says that it will respond to stage 2 complaints within 20 working days. If it cannot achieve this it will let the customer know why.
- However, in this case the landlord took 27 working days to respond to the stage 2 complaint. It did not agree an extension with the resident or let her know the reason for the delay. This failure to follow the policy meant that the resident was waiting longer for a resolution which caused her further distress and inconvenience. It also further delayed her access to an investigation by this Service.
- The landlord offered £50 at stage 2 of the complaints process for the delay in the stage 1 complaint response. However, it did not acknowledge the distress and inconvenience caused by the further delay at stage 2. Therefore, there was service failure in its handling of the resident’s complaint.