Social Tenant Access to Information Requirements (STAIRs) consultation is now open. 

Take part in the consultation

Southwark Council (202331912)

Back to Top

 

Decision

Case ID

202331912

Decision type

Investigation

Landlord

Southwark Council

Landlord type

Local Authority / ALMO or TMO

Occupancy

Leaseholder

Date

24 October 2025

Background

  1. The resident raised concerns about the remedial works following a leak into his property. He remained unhappy with the landlord’s response and requested for the outstanding works to be resolved.

What the complaint is about

  1. The complaint is about the landlord’s handling of the resident’s concerns about the remedial works following a leak into the property.
  2. We have also assessed the landlord’s complaint handling.

Our decision (determination)

  1. There was maladministration in the landlord’s handling of the resident’s concerns about the remedial works.
  2. There was maladministration in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

  1. The landlord failed to respond to the resident’s concerns about the remedial works in a timely manner. It also did not go far enough to put matters right where it identified failings.
  2. The landlord failed to fully engage with the resident’s complaint and did not offer reasonable redress for its delayed stage 2 response.

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1           

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

21 November 2025

2           

Compensation order

The landlord must pay the resident £400 made up as follows:

  • £200 for the distress and inconvenience caused by its handling of the remedial works.
  • £200 for the distress and inconvenience caused by its complaint handling failings. 

The landlord must provide documentary evidence of payment by the due date.

No later than

21 November 2025

 

3           

Action Order

The landlord must:

  • Contact the resident to discuss any outstanding concerns that he may have in relation to his 2023 complaints.
  • Remind staff of the importance of fully engaging with a complaint to ensure all concerns are appropriately responded to.
  • Remind staff that when required it should advise residents of its response timescales and implement relevant measures to effectively manage high volumes of communication as soon as possible.

It must provide documentary evidence that it has complied with this order by the due date.

No later than

21 November 2025

Recommendations

Our recommendations are not binding, and a landlord may decide not to follow them.

Our recommendations

The landlord should contact the resident to discuss his concerns that the dry rot may have spread and respond to his request for a property inspection.  

 

Our investigation

The complaint procedure

Date

What happened

September –November 2022

There was a leak in September 2022 from the property above the resident’s which caused damage to his flat. While unclear the evidence suggests that the leak was resolved around the end of October 2022.

In November 2022 the loss adjustor (Party A) inspected the resident’s property and recommended that the landlord replace the timber joists.

February 2023

A different loss adjustor (Party B) was assigned to the matter and carried out another property inspection. It said that the joists were the landlord’s responsibility and acknowledged that it would repair them.  It also recommended that the landlord should repoint the external brickwork.

The landlord’s contractor also carried out an inspection of the resident’s property at this time and provided a report of its findings.

13 April 2023

The resident made a complaint. Within this, he:

  • Said he had concerns about the contractor’s report. The author’s name was withheld and their qualifications were not listed. He explained that he had tried to obtain further details from the contractor, but it did not reply. He wished for the landlord to provide him with this information.
  • Asked the landlord to investigate the dry rot in his kitchen.
  • Asked the landlord to temporarily remove acrow props from his flat so he could complete some works in preparation for the upcoming inspection on 21 April 2023.

19 April 2023

The landlord issued its stage 2 response. It said:

  • It was unable to provide details of the author of the contractor’s report due to the General Data Protection Regulation (GDPR).
  • It was unable to remove the acrow props because they provided stability to the structure to the resident’s flat and building. It said it would be too dangerous for the resident to carry out any work.
  • It confirmed that it would inspect the dry rot in the resident’s kitchen on 21 April 2023 and discuss his concerns further then.

September 2023

During September 2023 the resident raised several queries and reported issues with the landlord. Some of them were reported through his MP. These included:

  • The contractor had caused a prolonged leak when it disconnected his washing machine. He said that the contractors had told him that it would install dehumidifiers.
  • The contractor had damaged some of his personal belongings when it left them outside. He said that the matter would be considered by the insurers, but wanted the landlord to be aware of the situation.
  • The contractors had not put locks on his flat doors.
  • The landlord should replace the joists rather than repairing them. He asked the landlord to seek legal advice. He also said that the landlord should carry out the external pointing work as recommended by Party B.
  • Concerns that there was not a party wall agreement in place. Therefore although work had started he had not consented to it.
  • A lack of communication and response to emails.

October 2023

On 5 October 2023 the resident escalated his complaint. He said that the landlord’s officer (Officer A) had not respond to his emails. He said he could provide information to show which of his concerns were left unaddressed.

22 November 2023

The landlord issued its stage 2 response. It said:

  • Officer A had left the organisation, therefore it was limited as to what records it could access. 
  • It had reviewed a number of enquiries submitted by the resident throughout August and September 2023. In doing so, it could see that there were a number of responses to the resident’s correspondence at that time.
  • However, it noted that the resident’s email to Officer A on 25 September 2023 had not been responded to. It apologised for the inconvenience that had been caused and responded to each point in turn, as follows:
  • A dehumidifier was not considered necessary following the washing machine leak, given the volume of water concerned. The resident had reported the leak to his insurers. It was unable to respond to his query and advised the resident to contact his insurers.
  • The resident’s claim for his damaged possessions was being dealt with by the contractors insurers. Therefore it was unable to comment as it not within scope of its complaint process.
  • It would check with its contractor about the locks and provide an update.
  • The resident should contact the loss adjustor directly if he had concerns about its decision about the external work. It would be considering next steps in relation to inspecting the pointing further and would update the resident.
  • It would not be seeking advice from its legal services. It had acted on the decision of the Party B in relation to the joists repairs. The method of repair was accepted and recognised as a way of addressing the issue and the loss adjustors were satisfied that repairs were justified and acceptable.
  • It had sought advice about the party wall agreement. It could not be served retrospectively. It apologised that it did not send its letter of written consent in lieu of the agreement. It said that the resident could seek legal advice on the matter. 
  • It could see that the resident had emailed its new officer on 20 October 2023 but he had not received a response. It explained that its officers aimed to respond to enquiries within 10 working days. It said that this may not always be possible due to limited resources and during busy periods. It asked to allow at least 10 working days for a response before chasing up any enquiries.
  • It upheld the resident’s complaint and apologised for its failings identified with its communication with the resident.
  • It had noted that the resident had enquired about the windows and it would provide a response once it had spoken to the contractor.

Referral to the Ombudsman

The resident remained unhappy with the landlord’s final response. In recent communication with our Service, he explained that he would like the landlord to resolve the outstanding works and issues that he highlighted in his “snag list” in 2024, pay its contractors and provide him with the dry rot guarantee.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of the resident’s concerns about the remedial works following a leak into his property.

Finding

Maladministration

  1. The resident raised additional issues to the landlord which included concerns about fire alarms, workmanship relating to the windows and joist repairs and a boiler leak. The evidence shows that these issues were raised after the landlord had issued it stage 2 response. In the interest of fairness, we are unable to investigate these concerns as the landlord has not yet had the opportunity to consider them through its formal complaints process. Our investigation has instead focussed on matters that were raised in 2023, and that the landlord responded to within its stage 2 response.

The dry rot works

  1. In response to the resident’s concerns about the joists, the landlord explained that Party B was satisfied that it would repair them. Therefore it would not replace the joists as recommended by Party A.
  2. We acknowledge that receiving different recommendations for the joist works from the two loss adjustors would have caused the resident confusion. It is also noted that the landlord’s decision not to replace the joists would have been disappointing for the resident.
  3. However, the landlord was entitled to rely on the recommendation that had been provided in the circumstances. Given that it was responsible for the repair, the landlord had the discretion to decide how to proceed. We are satisfied that it exercised its discretion fairly.  The landlord also appropriately informed the resident that he could seek legal advice about the matter if he was still concerned about its decision.
  4. On 11 October 2023 the landlord told the resident via his MP that it had challenged Party B’s recommendation to carry out external pointing work and that it had agreed with the landlord that it was not needed. It is within the landlord’s remit to discuss and challenge recommended works with agencies such as Party B. It said that the resident could raise his concerns directly with Party B. This was reasonable in the circumstances.
  5. The landlord updated the resident on 7 December 2023. It stated that as the 2022 leak did not penetrate the external wall, there was no need to carry out any works. It reasonably explained that if works were needed in the future it would carry them out as part of its major works programme.
  6. In response to the resident’s concerns about the windows, the landlord said it would respond to his enquiry once it had spoken to its contractor. While unclear the evidence suggests that the resident was enquiring about whether the windows would be replaced or renewed as he was concerned about the dry rot affecting them. In December 2023 the landlord told the resident that it would repair and replace them where required. The landlord confirmed that it would respond to any issues affecting the windows in line with its obligations, and this was reasonable in the circumstances.
  7. It is noted that over the months that followed, the resident raised concerns that the contractor said that it would replace the windows where dry rot was within 1 meter of a window. He said that this was the case with some of the windows that had not been marked for replacement. It is noted that in July 2024, the landlord reiterated its stance and said that it had followed the industry guidelines and that it would repair the windows, not replace them.
  8. It is acknowledged that the resident would like the joists and windows replaced. However, we are satisfied that at the time of the resident’s complaint, the landlord had responded appropriately to his concerns. The landlord has stated that the dry rot works were completed in early 2024. However, the resident has told us that the dry rot may have spread and he would like the landlord to carry out an inspection and complete any further works. He also stated that he has not received the dry rot guarantee. Therefore a recommendation has been made for the landlord to look into this matter and respond to the resident’s concerns.  The resident may also wish to seek legal advice on the matter.

Washing machine leak

  1. In its stage 2 response, the landlord stated that dehumidifiers were not necessary given the volume of water that had escaped. However, on 27 November 2023 the resident told the landlord that the contractor did install the dehumidifiers. It has not been possible for us to establish why the contractor had provided the resident and landlord with differing messages around this. It is acknowledged that the landlord was acting on the advice it had been given. However, the conflicting information and responses was understandably the cause of concern for the resident.
  2. The resident expressed concern about the leak and the impact of a further escape of water. In December 2023 the landlord explained that the washing machine leak did not mean that dry rot would occur. However, it would speak to the contractors in relation to the works it said it would carry out to resolve the issue. It is noted that the landlord provided further clarification on what action it would take to ensure any potential damage from the washing machine leak would be repaired. This was reasonable.

The resident’s belongings

  1. In its stage 2 response, the landlord said that it was unable to comment on the resident’s concerns that its contractors had caused damage to his personal belongings because the matter was with the insurers. This was reasonable in the circumstances given that a claim was underway, that the matter concerned the contractor (as opposed to landlord staff) and the issue of liability was not for the landlord to decide.

The door locks

  1. The evidence suggests that the resident was concerned that the contractor had not placed the locks on some of his doors. He was concerned that dust would settle on his belongings and contaminate them. He was also concerned that they may also be stolen when the contractor left the doors open.
  2. In its stage 2 response, the landlord said that it would speak to the contractor and provide an update. This was reasonable. On 7 December 2023 it said that it was still awaiting an update from the contractor. It is unclear whether the landlord provided an update on the matter after this and provided a response to whether the locks would be installed or not.
  3. It is noted that locks were not subsequently installed. We cannot comment on this, but the resident may wish to raise a complaint specifically about the decision not to install locks now. If he remains unhappy with the response he receives, he may refer the matter back to us as a new complaint.

The party wall agreement

  1. In September 2023, the landlord’s legal department advised that as the works had already started a party wall agreement could not be issued retrospectively. It explained instead the landlord should create a written agreement for the leaseholders to sign for its records.
  2. In its stage 2 response, the landlord apologised that it did not issue the written agreement as advised. While the apology is acknowledged, the landlord did not go far enough to put matters right. It failed to follow through with issuing its written agreement which meant that it missed an opportunity to resolve the resident’s concern that he had not consented to the works. That caused him distress and inconvenience.
  3. It is noted that the landlord explained that the resident could seek legal advice on the matter. This was reasonable. However, the additional time and trouble that the resident would incur by seeking legal advice on the matter may have been avoided, if the landlord had either issued a party wall agreement or issued the written agreement. Therefore given the circumstances, it would have been reasonable for the landlord to have offered the resident compensation for this failing. That it did not was a missed opportunity to put matters right.
  4. If the resident is concerned about any detriment caused as a result of not having a party wall agreement, he may wish to seek independent legal advice.

The landlord’s communication

  1. The landlord acknowledged and upheld the resident’s complaint about its lack of communication. While it is noted that it apologised for the failing, this did not go far enough to put matters right. The evidence shows that the resident had to wait for approximately 2 months for responses to some of his queries, including his concerns about the locks. This was outside of the landlord’s expected timescales of 10 working days. It is noted that some of the matters were complex and that third parties were involved; however, we have not seen evidence that the landlord was proactive in keeping the resident updated.
  2. The manner in which the landlord handled and responded to the resident’s communication was the cause of further distress and inconvenience. While this was acknowledged by the landlord during the complaints process, it failed to take steps to try to put things.
  3. In its stage 2 response, the landlord provided an assurance that it would respond to the resident’s enquiries within 10 working days. This demonstrates that it had learnt from the complaint in relation to communication. It is also noted that it asked the resident to avoid following up on his enquiries during that 10-working day period. This was a reasonable request and would help to ensure that a timely response could be provided. However, given the evidence we have seen, it is unclear why the landlord did not take the opportunity to try to manage the resident’s communication sooner. This was not a failing, but rather a shortcoming in the circumstances.

Complaint

The landlord’s complaint handling

Finding

Maladministration

  1. On 2 November 2023 the landlord informed the resident that due to its complaint caseload it had to extend its response deadline to 17 November 2023. The landlord’s explanation and its 10-working day extension was compliant with our Complaint Handling Code (the Code). Therefore its actions at this time were reasonable.
  2. However, it did not issue its stage 2 response until 22 November 2023. It is noted that it updated the resident that there would be further delays on or around 13 November 2023. Nonetheless, the 13-working day delayed response would have caused the resident distress and inconvenience. Given the length of delay, it would have been reasonable for the landlord to have offered the resident compensation for its failing to meet its timescales. That it did not was a missed opportunity to put matters right.
  3. When the resident escalated his complaint, he told the landlord he had copies of correspondence which had been left unanswered that he could provide. However the landlord did not follow up on the resident’s comment. Given that Officer A had left the organisation and the landlord expressed that it was unable to access his emails, that it did not contact the resident to appropriately ascertain what queries were left unanswered was unreasonable.
  4. In particular as the evidence shows that the resident raised further questions after the landlord had issued its stage 2 response. In that correspondence he also explained that he had not received a response from Officer A about his concerns that the gas pipe was sagging. This further time and trouble incurred may have been avoided if the landlord reasonably ensured that it had understood what queries were left unanswered. That it did not was a missed opportunity to ensure it had fully and meaningfully addressed the resident’s complaint within its complaint responses. That was unreasonable.
  5. It is unclear whether the landlord reasonably addressed his concerns at a later date as the resident raised concerns about the gas pipe in 2024. Taking this into consideration and the landlord’s complaint handling failing, an order has been made for the landlord to contact the resident to discuss any outstanding concerns that it did not address in its complaint response. These should be in relation to his 2023 concerns and the landlord should provide a written response. If it is unable to address any of the queries, it should provide a reason as to why.
  6. It is noted that the resident had raised concerns throughout this situation that the landlord had taken 3 months to fix the initial leak, including through his MP. While the landlord responded to some of the resident’s questions at the time, there is no evidence that it addressed his specific concerns about the length of time it took to resolve leak. It is acknowledged that the landlord may not have considered that the resident’s comments were a complaint. However, given that he repeatedly raised the concern, it would have been reasonable for it to have addressed it. That it did not was a missed opportunity to ensure that the resident’s concerns were fully answered. Given the above failings, there was maladministration in the landlord’s complaint handling.

Learning

Knowledge information management (record keeping)

  1. We did not receive a copy of the resident’s 25 September 2023 email. It is noted that there was a high volume of information in relation to this case. Therefore it is unclear whether the landlord had the email on file and failed to provide a copy of it to us. Or that it did have a copy of it on its record. In addition, the landlord explained in its stage 2 response that it would not have access to emails in relation to the resident’s correspondence between him and Officer A. These issues may be indicative of recording keeping issues which the landlord may wish to review.