Peabody Trust (202544131)

Back to Top

 

Decision

Case ID

202544131

Decision type

Investigation

Landlord

Peabody Trust

Landlord type

Housing Association

Occupancy

Shared Ownership

Date

2 June 2026

Background

  1. The resident reported uneven paving in a communal area to the landlord on several occasions. He was unhappy with its response and time taken to complete the repair.

What the complaint is about

  1. This complaint is about the landlord’s handling of the resident’s:
    1. Reports of uneven paving.
    2. Complaint.

Our decision (determination)

  1. We have found:
    1. Maladministration in the landlord’s handling of the resident’s reports of uneven paving.
    2. Service failure in the landlord’s handling of the resident’s complaint.
  2. We have made orders for the landlord to put things right.

Summary of reasons

The landlord’s handling of the resident’s reports of uneven paving

  1. The landlord did not complete the repair in line with the timescales set out in its repairs policy. Its communication with the resident was poor. It did not fully resolve the matter through its internal complaint procedure.

The landlord’s handling of the resident’s complaint

  1. The landlord did not handle the resident’s complaint in accordance with the timescales set out in its complaint procedure. It offered some compensation. However, this was not proportionate to the delays experienced by the resident.

 

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure it has due regard to our apologies guidance.

No later than

07 July 2026

2

Compensation order

The landlord must pay the resident £575 made up as follows:

  • £500 for the distress and inconvenience caused by its handling of his reports of uneven paving

 

  • £75 for the distress and inconvenience caused by its handling of the complaint

 

This includes the compensation offered at stage 2.

 

The landlord must pay this directly to the resident by the due date.

 

The landlord must provide documentary evidence of payment by the due date. It may deduct from the total figure any payments it has already paid.

 

No later than 07 July 2026

3

Clarification order

The landlord must write to the resident to set out its final position concerning the repair. It must confirm the completion date of the works if applicable. If the repair is still outstanding, it must set out a repair action plan in writing, including timescales.

No later than 07 July 2026

 

 

 

 

Our investigation

The complaint procedure

Date

What happened

30 August 2025

The resident complained that the landlord had not yet repaired uneven paving he said he reported in June 2025. He felt it posed a safety risk, was worsening, and criticised its poor communication.

5 September 2025

Following an email from the landlord on 4 September 2025, the resident informed it that his previous correspondence was a formal complaint and not a service request.

17 October 2025

The landlord acknowledged the complaint at stage 1.

14 November 2025

The landlord issued its stage 1 complaint response. It said it had failed to raise and manage the repair promptly, causing delays and poor communication. It said it had raised a new work order, approved the quote, and works would start shortly. It apologised and offered £200 compensation. This comprised £100 for distress and inconvenience, £75 for poor communication, and £25 for the delayed complaint response.

21 November 2025

The resident requested escalation of his complaint.

18 December 2025

The landlord issued its stage 2 complaint response. It said it carried out the repair on 22 and 23 November 2025. It apologised for the delay and explained this was due to the complexity of the repair and a restructure of its services. It offered the resident a further £125 compensation, £25 for complaint handling and £100 for the repair delay. This resulted in a total compensation offer of £325.

Referral to the Ombudsman

The resident was unhappy with the landlord’s final complaint response and referred the matter to us. He said he did not receive the compensation offered by the landlord. He also said the repair remained unresolved as it was still uneven and unsafe. To resolve the complaint, he wanted it to complete the repair, pay additional compensation, and review its procedures.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of the resident’s reports of uneven paving

Finding

Maladministration

  1. The resident said he reported uneven paving in June 2025 and made repeated requests for updates. The landlord said it raised 2 work orders on 19 July 2025. It has not provided records of the initial report, the work orders, or copies of his communications. This indicates poor record keeping and has limited our ability to assess its response.
  2. The landlord’s responsive repairs policy confirms it was responsible for maintaining communal areas where it was the freeholder. Although neither party has provided a copy of the lease, there is no evidence to dispute that this obligation applied. Its policy also states it will carry about regular inspections to check for repairs in communal areas. It has not provided evidence of inspections or whether it identified the paving issue as a potential hazard.
  3. The landlord said contractors attended on 22 July 2025 but could not complete the repair as the operatives did not have the correct skillset. It has not provided a report or evidence from this visit. We have also seen no evidence that it promptly arranged a follow-on appointment with suitably skilled operatives or that it kept the resident informed. This reflects a failure to manage the repair effectively and avoidable delay.
  4. Following the resident’s complaint in August 2025, the landlord raised a further work order, demonstrating that the resident had to pursue the matter to progress the works. It has not evidenced any consideration of risk, which was inappropriate considering the nature of the outstanding repair.
  5. At stage 2, the landlord said it completed the repair on 23 November 2025. It has not provided any records of the repair attendance, or evidence to demonstrate how it assured the quality of the completed work.
  6. In September 2025, the landlord initially advised the resident that it did not compensate for communal repairs. This was not consistent with its compensation policy, which says it will consider compensation and other remedies if it fails to carry out a service within its published guidelines. It also says it will consider payments for distress and inconvenience when a situation has impacted a resident.
  7. The landlord acknowledged delays and poor communication within its final complaint response and awarded £275 compensation, excluding complaint handling. In line with our compensation guidance, this was broadly proportionate for failures causing distress and inconvenience without permanent impact. However, the repair remained unresolved. The same day it issued its final complaint response, the resident reported the works were unsuccessful and the paving remained uneven.
  8. While a repair being unsuccessful in isolation does not necessarily amount to a service failure, the absence of supporting records, post‑inspection, or quality checks undermines the landlord’s position that it appropriately addressed the matter. Furthermore, there is no evidence that it set out clear next steps to the resident following the failed repair. This lack of communication, combined with delays in progressing the repair within the expected 60-day timeframe for complex works, represents a failure in service delivery.
  9. The landlord has provided limited evidence of its actions post-complaint, although it referred to further investigations involving external specialists. It confirmed that it had scheduled additional remedial works to begin on 18 May 2026, almost 11 months after the resident said he initially reported the issue. This indicates it did not provide an effective and lasting repair within a reasonable timeframe. However, we appreciate the repair was more complex than it initially considered. We contacted it to ask for more information about the status of the repair, however it has not provided this.
  10. Our compensation guidance explains that we can consider compensation up until the landlord corrects the failing or until the determination date, whichever is earlier. We do not order compensation beyond the determination date. The available evidence does not confirm whether the remedial works started on 18 May 2026, nor whether the repair was completed.
  11. In view of this uncertainty and the period under consideration, we have determined that the landlord should pay the resident an additional £225 in compensation. This is in addition to the £275 previously offered at stage 2, excluding compensation for complaint handling which we have considered separately below. This brings the total compensation to £500.
  12. This award falls within our range of financial redress set out in our compensation guidance. This is applicable where failings have adversely affected a resident but have not resulted in permanent impact.

Complaint

The landlord’s handling of the resident’s complaint

Finding

Service failure

  1. Under the Complaint Handling Code (the Code), landlords must acknowledge complaints within 5 working days. It must issue stage 1 responses within 10 working days of acknowledging a complaint. Stage 2 responses are due within 20 working days. This is extendable by up to 10 and 20 working days respectively in agreement with the resident.
  2. The landlord’s complaint procedure aligns with the Code in respect of complaint definition and response timescales. However, it was not compliant with the Code regarding its stage 2 extension timescale of 10 working days. We have identified a learning point on this issue.
  3. The resident complained on 30 August 2025. The landlord acknowledged this 35 working days later, on 17 October 2025 after further contact from him. This was significantly outside Code requirements. It issued its stage 1 response 20 working days after acknowledgement, with no evidence of an agreed extension. It also failed to acknowledge his escalation request. It provided its stage 2 response within its policy timescale.
  4. The landlord offered a total of £50 compensation for its complaint handling failings. In line with our compensation guidance, this does not reflect the extent of delay and service failure, which went beyond minor shortcomings. A higher award is appropriate for delays of this duration. Accordingly, we have made a finding of service failure, with an additional £25 compensation ordered.
  5. We have considered the landlord’s acknowledgement of failings and apology, as well as the learning set out within its complaint response. We have taken these into account, as without them, a finding of maladministration for complaint handling may have applied.

Learning

General learning

  1. The landlord ought to ensure its complaints policy fully aligns with the Code in terms of extension timescales.
  2. The resident provided evidence that he provided his bank details to the landlord and said it had not paid compensation. The landlord said it did not receive these. The landlord ought to consider how it processes offers of compensation post complaint.

Knowledge information management (record keeping)

  1. Good record keeping ensures that repairs and works are managed effectively without the need for repeat reports or unreasonable delays. It also supports our investigation if the landlord provides detailed information relating to repairs and communication. The landlord may wish to review our Spotlight Report on Knowledge and Information Management.
  2. When repairs remain outstanding after the stage 2 complaint response, it is important that landlords provide updated information to us about the status of the repair.

Communication

  1. Effective communication is vital. Poor communication leaves residents uninformed, leading to frustration and repeated contacts. Clear, timely updates help manage expectations, reduce repeat contact, and highlight areas where processes or oversight need improvement. The landlord may wish to review our Spotlight Report on Repairing Trust.