London & Quadrant Housing Trust (202429630)
|
Decision |
|
|
Case ID |
202429630 |
|
Decision type |
Investigation |
|
Landlord |
London & Quadrant Housing Trust |
|
Landlord type |
Housing Association |
|
Occupancy |
Leaseholder |
|
Date |
28 October 2025 |
Background
- The resident lives in a 2-bedroomed flat on the top floor of a 3-storey block. She has anxiety and has recently had oncology treatment. She has complained about a leak from the roof which is affecting her property. She escalated her complaint to the Ombudsman because she is not satisfied with the landlord’s response.
What the complaint is about
- The complaint is about the landlord’s:
- Response to reports of a leak from the roof as well as damp and mould in the resident’s property.
- Complaint handling.
Our decision (determination)
- We have found that:
- There was maladministration in the landlord’s response to reports of leak from the roof and damp and mould.
- There was maladministration in the landlord’s handling of the complaint.
We have made orders for the landlord to put things right.
Summary of reasons
The handling of reports of a leak and damp and mould
- Although the landlord inspected the roof promptly in line with its policy, it did not act on the recommendations of its surveyor. It delayed completing the necessary works to the roof that were raised in the inspection. This led to damp and mould in the resident’s flat.
The complaint handling
- The landlord did not monitor progress to ensure all actions set out in its complaint response were completed. It did not communicate with the resident, forcing her to chase updates and leaving her unaware of the action taken. It did not escalate the complaint when this was requested by the resident.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order
The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:
|
No later than 26 November 2025 |
|
2 |
Inspection order
The landlord must contact the resident to arrange an inspection. It must take all reasonable steps to ensure the inspection is completed by the due date. The inspection must be completed by someone suitably qualified to complete an inspection of the type needed. What the inspection must achieve The landlord must ensure that the surveyor:
The survey report must set out:
|
No later than 26 November 2025 |
|
3 |
Compensation order The landlord must pay the resident £770 made up as follows:
This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date. The landlord may deduct from the total figure any payments it has already paid.
|
No later than 26 November 2025 |
Our investigation
The complaint procedure
|
Date |
What happened |
|
15 July 2024 |
The resident complained that every time it rains water leaks through the roof. This had been a reoccurring issue for over 10 years. This is causing black mould in the hallway of her flat. |
|
16 July 2024 |
The landlord responded at stage 1 of the complaint process and apologised for the ongoing issues. It advised that it had chased the contractor and roofing team to action the outstanding works and would update the resident when it had a response. |
|
8 August 2024 |
The resident contacted the landlord as there was still no update regarding works, the leak was still ongoing. She asked how to escalate the complaint. |
|
18 September 2024 |
The resident said that rainwater continues to come into her flat and the landlord has not addressed it in a timely manner. There is black mould growing in her flat as a result. She again requested that her complaint be escalated to stage 2. |
|
21 October 2024 |
The landlord responded and said that the contractor had attended on 21 March 2024 and carried out a drone survey. The job had since been closed and referred to the surveyor to escalate. The roofing team would contact the resident regarding follow up works. The landlord awarded the resident £140 compensation made up of:
|
|
Referral to the Ombudsman |
The resident escalated her complaint to the Ombudsman because the issue is ongoing, and the landlord has not communicated a plan or timeframe. |
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
The handling of reports of a leak and damp and mould. |
|
Finding |
Maladministration |
- The occupancy agreement states that the landlord is responsible for repairs to the roof of the building. Leaseholders are responsible for all repairs to the interior of their property. The repairs policy states that it aims to complete routine day to day repairs in an average of 25 calendar days. There is no service standard for more complex major works.
- The resident reported the leak to the roof on 10 March 2024. The landlord asked a contractor to inspect the roof on 21 March 2024. This was 8 working days after the repair was reported. The contractor made recommendations to the landlord to rectify the leak. Contractors would need scaffolding for further works. The landlord reviewed the contractor’s quote for the works and declined it.
- We do not know what happened after the roofing team declined the quote. However, the works remained outstanding for 8 months. Although the works needed were complex in nature, the landlord delayed its response to the recommendations. Repairs were completed on 26 November 2024. This was 183 days after the initial report.
- The Ombudsman’s Spotlight Report on Repairs (published in May 2025) stresses the importance of communication between landlords and residents. Ineffective communication leaves residents uninformed and frustrated. One of the recommendations in the report was for landlords to review communication to ensure it is “timely, transparent, tailored”.
- The resident chased the repair multiple times in the lead up to her stage 1 complaint on 15 July 2024. In its stage 1 response the landlord said it would update the resident as soon as it had information about the outstanding works. However, the resident had to chase the repair several more times between her stage 1 and stage 2 complaints.
- Following the stage 2 response on 21 October 2024, the landlord did act on the repair. Works were started around 23 October 2024 and signed off on 26 November 2024. However, this information was not communicated to the resident. She is under the impression that the landlord had attempted a temporary fix. The resident confirmed to the Ombudsman that the leak was still present in February 2025.
- The landlord’s damp and mould policy states that it will tackle the root cause of the problem and carry out repairs needed to prevent damp and mould from reoccurring. Damp can be caused by water penetration through leaks. After a report of damp and mould, an inspection should take place within 20 working days and any remedial works identified will be raised within 10 working days of the inspection.
- The landlord’s vulnerable residents policy defines a vulnerable resident as someone with a condition or circumstance that places them at risk in their home. The policy states that residents can be supported in several ways, including providing minor health and safety repairs at no cost and prioritising health and safety repairs.
- On 14 July 2024 the resident advised the landlord that there was black mould inside her property due to the ongoing roof leak. Although the interior of the flat is the resident’s responsibility, the damp and mould could have been linked to the ongoing water penetration. The resident further advised the landlord on 11 September 2024 that she was undergoing oncology treatment which left her at risk of infection. The situation was also causing her anxiety and stress. It would have been reasonable for the landlord to inspect her property to see if the leak was causing damp and mould. It could have looked at how this could be mitigated, for example, providing a dehumidifier or carrying out a mould wash. The landlord did not inspect the resident’s property or offer any support with the damp and mould.
- Overall there was maladministration in the landlord’s handling of the reports of a leak and damp and mould.
|
Complaint |
The handling of the complaint |
|
Finding |
Maladministration |
- The landlord’s complaints policy states that it will acknowledge a complaint within 5 working days, respond to a stage 1 complaint within 10 working days and to a stage 2 complaint within 20 working days.
- The landlord acknowledged and responded to the resident’s stage 1 complaint on time. However, it did not act on the resident’s request for her complaint to be escalated to stage 2. She emailed requesting escalation on 8 August 2024 and had to chase this with the landlord on 18 September 2024. The response to the stage 2 complaint took 52 working days from her first escalation request. The landlord offered compensation of £20 for this service failure, however this was not reasonable redress for such a long delay.
- The stage 1 response did not address the length of time the issue had been ongoing or what action had been taken previously. The stage 2 response did not acknowledge the failings in the stage 1 response or in the escalation to stage 2.
- The complaints policy states that after the landlord’s decision is confirmed in writing, it will monitor progress until all outstanding actions are complete.
- At both stages of the internal complaint procedure, the landlord stated that it would keep the resident updated and make contact regarding appointments. This did not happen. The resident had to contact the landlord multiple times for updates. She remains unaware of the outcome of works following her stage 2 complaint. This amounts to maladministration.
Learning
Knowledge information management (record keeping)
- Although the landlord had access to the contractor’s inspection report, this was not shared between teams so that complaint handling staff could respond in detail to the resident’s stage 1 complaint. The landlord should act promptly with the information it has available.
Communication
- The landlord’s communication with the resident was poor in this case. The promised updates would have eased the resident’s concern and frustration and saved her the time and trouble of chasing information and submitting complaints.
Repairs and damp and mould
- The landlord caused unnecessary delays by declining the roof quote from the contractor and not rescheduling works. The resident had damp and mould in her property, which was not addressed by the landlord despite the possible link to water penetration.
Complaint handling
- The landlord should act promptly to requests to escalate complaints. Its responses should address all points raised and put things right. The landlord should monitor progress and keep residents updated.