London Borough of Ealing (202314014)

Back to Top

 

Decision

Case ID

202314014

Decision type

Investigation

Landlord

London Borough of Ealing

Landlord type

Local Authority

Occupancy

Assured Tenancy

Date

28 March 2026

Background

  1. The resident reported a leak from the roof, which was coming through the toilet ceiling, on 3 November 2022. The landlord repaired the roof and resolved the leak on 2 May 2023. The resident made a complaint to the landlord on 18 July 2023. She expressed dissatisfaction at the delay in it resolving the leak and the fact that it had still not repaired the damage caused to the toilet ceiling. She said she was also waiting for the landlord to complete repairs to her kitchen and inspect damage to the exterior brickwork.

What the complaint is about

  1. The complaint is about the landlord’s handling of repairs to a roof leak, the toilet ceiling, kitchen and brickwork.
  2. We have also assessed the landlord’s complaint handling.

Our decision (determination)

  1. There was maladministration in the landlord’s handling of repairs to a roof leak, the toilet ceiling, kitchen and brickwork.
  2. There was service failure in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

  1. The landlord delayed unreasonably in completing the repairs and has still failed to address all outstanding issues. Its failure to proactively communicate with the resident about asbestos in the property also caused her significant distress and anxiety. While the landlord made an offer of redress to the resident, this was not proportionate to the level and duration of its failings.
  2. The landlord failed to provide its stage 2 complaint response within the timescale required by its policy and our complaint handling code (the Code). It has not provided any evidence it communicated with the resident about this delay as its policy required. The landlord also failed to address the resident’s concerns about brickwork in its stage 1 or 2 complaint responses, which led to us asking it to issue a further ‘reviewed’ stage 2 complaint response months later.

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

20 April 2026

2

Compensation order

The landlord must pay the resident £700 made up as follows:

  • £600 for the distress and inconvenience caused by its handling of repairs
  • £100 for the time and trouble caused by its complaint handling.

This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date.

The landlord may deduct the £250 offered in its complaint responses from the total figure if it has already paid this.

No later than

20 April 2026

3

Inspection order 

The landlord must contact the resident to arrange an inspection. It must take all reasonable steps to ensure the inspection is completed by the due date. The inspection must be completed by a suitably qualified person. If the landlord cannot gain access to complete the inspection, it must provide us with documentary evidence of its attempts to inspect the property no later than the due date.  

What the inspection must achieve 

The landlord must ensure that the inspector: 

  • Inspects the kitchen door frame and tiling, toilet floor and pipework boxing, and the exterior brickwork of the property 
  • Produces a written report with photographs 

 The survey report must set out: 

  • Whether the landlord is responsible to repair or resolve the issue together with reasons where it is not responsible 
  • A full scope of works to achieve a lasting and effective repair to the issues (if the landlord is responsible) 
  • The likely timescales to commence and complete the work 

No later than

20 April 2026

 

Recommendations

Our recommendations are not binding, and a landlord may decide not to follow them.

Our recommendations

During a phone call on 26 March 2026, the resident also raised concerns about the fencing at the property. While this is outside of the scope of this investigation, the landlord should inspect this when complying with the inspection order made above.

Our investigation

The complaint procedure

Date

What happened

18 July 2023

The resident made a complaint to the landlord she said that:

  • She had reported a roof leak on 3 November 2022. It had taken the landlord until 2 May 2023 to repair this.
  • The landlord had still not repaired the damage to the toilet caused by the leak.
  • She was also waiting for new worktops, tiles and taps in her kitchen.
  • She felt the kitchen sink and cupboards should also be replaced.
  • The roofer who had repaired the leak said there was a large crack in the brickwork of the property. She believed this may be causing mould.

10 August 2023

The landlord provided its stage 1 complaint response. It said that it had now raised orders for the required works to the toilet and kitchen.

17 August 2023

The resident asked to escalate her complaint to stage 2 of the landlord’s process. She said that she had been contacted by a contractor which advised it was unable to replaster the toilet ceiling due to it containing asbestos. The resident expressed concern about potentially being exposed to asbestos since the leak occurred on 3 November 2022. She also requested compensation for the stress of living for months with “water pouring in” through the roof which she had to mop up with towels.

13 October 2023

The landlord provided its stage 2 complaint response. It said that:

  • It had now completed most repairs to the kitchen. With just some tiling to finish.
  • It understood the resident’s concerns regarding asbestos, but she was “perfectly safe” in the property. The asbestos in the toilet ceiling was in the lowest risk category, and it was “almost impossible” it would be released “without direct disturbance”.
  • It was offering the resident £100 compensation for the delay in completing repairs and her time and trouble pursuing them.

Referral to the Ombudsman

The resident remained dissatisfied so brought her complaint to us. On 12 February 2024, we wrote to the landlord. We said that having reviewed the complaint, we did not feel it had addressed all complaint points raised by the resident in its responses. We suggested it may wish to review its stage 2 response to ensure it did so.

20 February 2024

The landlord provided a reviewed stage 2 complaint response. It said that it:

  • Had taken too long to repair the roof leak.
  • Had now completed all repairs to the toilet and kitchen.
  • Had asked a specialist contractor to treat any mould in the property and inspect to determine what the cause was.
  • Acknowledged the alarm that would have been caused by the contractor telling the resident the toilet ceiling contained asbestos. It had provided feedback regarding better informing residents about asbestos in their property and how to manage this.
  • Wished to offer the resident £150 compensation for the length of time taken to complete repairs and her time and trouble pursuing them.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The complaint about the handling of repairs to a roof leak, the toilet ceiling, kitchen and brickwork.

Finding

Maladministration

Roof leak

  1. In her complaint, the resident said that she first reported the roof leak to the landlord on 3 November 2022. This is supported by the landlord’s repair logs. The resident also said that the landlord took until 2 May 2023 to repair the leak. While it is unclear from the landlord’s records exactly when it repaired the leak, it did not contest the date of 2 May 2023 in either of its complaint responses.
  2. The landlord’s repairs policy says that it will complete routine repairs within 28 working days. It defines routine repairs as any repair which it does not consider an emergency. The landlord took 6 months to repair the resident’s roof leak. This significantly exceeded its policy timescale and was unreasonable. Particularly given the resident has told us that the repair an operative eventually completed the repair using just a ladder.
  3. The landlord’s records show that the resident contacted it repeatedly between November 2022 and March 2023 to chase up the repair and express concern about the water damage. Even after the landlord attended and boarded up the toilet ceiling, she told it that water was still pouring through the joins between the boards whenever it rained heavily. The resident has told us there is only one toilet in the property, so she was forced to use it even when water was leaking from the ceiling. This would have caused the resident significant distress and inconvenience during this period.
  4. In its reviewed stage 2 complaint response, the landlord acknowledged that it “took too long” to repair the roof leak. However, it failed to offer the resident any explanation for the delay – which appears to have been due to issues with its roofing contractor.

Toilet ceiling

  1. As noted above, the landlord boarded over the toilet ceiling until it could repair the roof leak. This was a reasonable temporary measure as the ceiling would continue to be damaged by rainfall until the leak was resolved.
  2. The landlord’s repair logs show that it raised a works order to a contractor on 17 March 2023. This was to renew the toilet ceiling once the roof leak was resolved. The landlord’s records show that the order was cancelled as the “contractor refused work”. Despite the roof leak apparently being repaired on 2 May 2023, we have seen no evidence that the landlord raised a further works order for the ceiling until over 3 months later, after the resident made her complaint. This was an unreasonable delay which had already exceeded its routine repair timescale.
  3. The landlord raised a works order to a new contractor on 10 August 2023. However, 4 days later it identified that the toilet ceiling contained asbestos. The landlord asked its contractor to put the work on hold while it arranged for this to be removed.
  4. We have not seen any evidence the landlord told the resident about this development, and the additional work required. This led to the resident escalating her complaint on 17 August 2023, after the landlord’s contractor informed her that it was putting the ceiling repairs on hold due to the asbestos. This caused the resident significant distress and anxiety as she feared her and her family may have been exposed to asbestos since the roof leak began affecting the ceiling months previously. This could have been avoided had the landlord contacted her and appropriately explained the situation once it became aware of the asbestos.
  5. In its stage 2 complaint response, the landlord appropriately explained to the resident that she was “perfectly safe” in her home. It said that the asbestos was in the lowest risk category and ‘trapped’ in the ceiling coating meaning that “fibre release is almost impossible without direct disturbance”.
  6. In its reviewed stage 2 complaint response, the landlord showed learning from the complaint – saying that it had provided internal feedback about communicating the results of asbestos surveys, and how to manage any asbestos present, to residents. It said it had also reminded its lettings team that they should be informing new residents of any asbestos present in the property as part of the lettings process. This was good practice in keeping with our dispute resolution principle to learn from outcomes of complaints.
  7. The landlord acted promptly and raised a works order for a specialist contractor to remove the asbestos on 14 August 2023. However, the work does not appear to have been completed until on or around 26 October 2023. The landlord has not provided any explanation for this significant delay. Following this, the landlord’s contractor repaired the toilet ceiling on 1 November 2023. It then returned a week later to redecorate the room.
  8. On the repair notes from this visit, the contractor recorded that the resident had told it a small area of the toilet floor had “dipped down and sunk in”. We have seen no evidence that the landlord followed up on this, and the resident has told us it is still outstanding. The resident has also told us that boxing in around the toilet pipes, which was damaged by the roof leak, was not repaired to her satisfaction. We have made an order above for the landlord to inspect these and raise any required works.

Kitchen repairs

  1. The landlord’s repair records indicate that it inspected the resident’s kitchen on 18 November 2022. This was in response to her reports that a section of the worktop was “rotten and sinking”. We have not seen any record of the inspections findings, or evidence of the landlord raising works orders based upon them.
  2. The landlord included the kitchen repairs in the works order that it raised on 10 August 2023, following the resident’s complaint. This represented a delay of almost 9 months between it inspecting the kitchen and raising the works, which was unreasonable. The landlord has not provided any explanation for this delay.
  3. After the landlord raised the works order, its contractor completed the kitchen works promptly on 29 August 2023. In its stage 2 response, 2 weeks later, the landlord acknowledged that some tiling work remained outstanding due to ‘differing colours’ but said it was investigating this.
  4. In its review stage 2 response, the landlord said it had “now replaced the tiles that were missing or broken”. However, the resident disputes this. She told us on 26 March 2026 that tiling directly above the worktop is still missing, leaving exposed wall. The resident also said that the landlord removed a section of her kitchen door frame to get the new work tops into the room and has not repaired this. We have ordered the landlord to inspect both issues as part of our inspection order above.

Brickwork

  1. In her original complaint, the resident said that the roofer who had repaired the leak had pointed out a large crack going through the brickwork and issues with the rendering on the outside of the property. She expressed concerns this could be contributing to mould in her bathroom.
  2. The landlord failed to acknowledge or respond to this concern in its stage 1 or 2 complaint responses. It was not until its reviewed stage 2 complaint response, over 6 months after the resident first made her complaint, that it did so. In this response the landlord said it would arrange for its damp and mould contractor to treat the mould and determine what the cause was.
  3. The damp and mould contractor attended promptly on 28 February 2024, 8 days after the landlord’s reviewed stage 2 complaint response. It treated the mould and identified loose pointing and gaps in the exterior brickwork. The landlord repaired these on 24 April 2024. However, the resident has told us there are still cracks in the brickwork, so we have included this in our inspection order too.

Summary

  1. Between its stage 2 and reviewed stage 2 complaint responses, the landlord offered the resident a total of £250 compensation for its delays in completing the repairs and the time and trouble taken by the resident in pursuing them.
  2. When considering whether an offer of compensation appropriately reflects the distress and inconvenience caused to a resident, we consider the level of failings, duration of them and the detriment caused. In this case the resident:
    1. Lived with an ongoing roof leak affecting her only toilet for a period of almost 6 months.
    2. Waited over 9 months for the landlord to complete repairs to her kitchen after it had inspected it.
    3. Repeatedly chased the landlord over its failure to log and complete necessary repairs in a timely manner.
    4. Was caused to fear she and her family had been exposed to asbestos for 9 months due to the landlord’s poor communication.
    5. Has told us that some issues are still outstanding over 2 years on from the landlord’s reviewed complaint response.
  3. The landlord’s offer of £250 does not reasonably reflect the severity of its failings over such a lengthy period. Due to this, we make a finding of maladministration and order the landlord to pay the resident a total of £600, inclusive of its original offer of £250. This is in keeping with our remedies guidance for instances where a landlord has made some attempt to put things right, but the offer is not proportionate to the failings identified by our investigation.

Complaint

The handling of the complaint

Finding

Service failure

  1. At the time of the resident’s complaint, the landlord’s complaints policy said that that it would respond to complaints within 20 working days at each stage of its process. It said that, where it needed to extend these timescales, it would inform the resident and give an expected date for its response.
  2. The landlord’s stage 1 timescale did not comply with the Code at that time, which required a stage 1 response to be issued within 10 working days of a complaint. However, during this period we allowed some discretion on timescales by local authority landlords, due to the fact their complaints policy covering numerous services with differing requirements. The landlord’s current policy is aligned to the latest version of the Code.
  3. The resident made her complaint on 18 July 2023, and the landlord provided its response 17 working days later, in keeping with its policy timescale.
  4. The resident escalated her complaint to stage 2 of the landlord’s process on 17 August 2023. The landlord failed to provide its stage 2 complaint response until 13 October 2023 – 41 working days later. We have not seen any evidence the landlord informed the resident of a delay or when she could expect to receive her response, as its policy requires. Nor did the landlord acknowledge the delay within the stage 2 response itself.
  5. After the resident referred her complaint to us, we suggested that the landlord reissue its stage 2 complaint response as it had failed to address all the resident’s complaint points. It had failed to provide any response or comment upon the concerns she raised about cracks and rendering damage to the brickwork in either its stage 1 or initial stage 2 responses. This was not in keeping with the Code, which says that “landlords must address all points raised in the complaint”.
  6. Due to these failings, we make a finding of service failure and order the landlord to pay the resident £100 compensation. This is in keeping with our remedies guidance for minor failures which did not affect the overall outcome for the resident.

Learning

  1. In its reviewed stage 2 complaint response, the landlord said that it had “introduced proactive monitoring” of repairs and was creating an information leaflet to give to residents with asbestos in their homes. This evidenced good learning from the complaint.

Knowledge information management (record keeping)

  1. The landlord’s records were generally clear and reasonably detailed. However, it failed to appropriately use these to manage and progress the repairs to the property.

Communication

  1. We have limited evidence of the landlord’s communications with the resident outside of its complaint responses. However, it is evident that the resident repeatedly contacted the landlord about the roof repairs between November 2022 and March 2023 and it failed to provide her with clear updates.