London Borough of Camden Council (202425657)
|
Decision |
|
|
Case ID |
202425657 |
|
Decision type |
Investigation |
|
Landlord |
London Borough of Camden Council |
|
Landlord type |
Local Authority / ALMO or TMO |
|
Occupancy |
Leaseholder |
|
Date |
2 April 2026 |
Background
- The resident reported a leaking stopcock on 24 June 2024. She told the landlord she was preparing to have bathroom works carried out and that her plumber had found the stopcock in the communal riser was corroded and unable to operate it.
What the complaint is about
- The landlord’s handling of:
- the repair to the stopcock
- the associated complaint
Our decision (determination)
- We have found there was:
- service failure in the landlord’s handling of the repair to the stopcock
- no maladministration in the landlord’s handling of the associated complaint
We have not made orders for the landlord to put things right.
Summary of reasons
The landlord’s handling of the repair to the stopcock
- The landlord failed to complete the repair within its 20‑working‑day policy timescale. It later acknowledged these failings and awarded compensation. However, this compensation would only have been reasonable if the landlord had followed through on the stopcock replacement it identified as necessary or clearly explained why it was no longer replacing it. Because the landlord did neither, the redress did not fully address the ongoing uncertainty or the impact on the resident.
Complaint handling
- The landlord responded to the complaint in line with its complaints policy at both stages.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:
|
No later than 05 May 2026 |
|
2 |
Compensation order The landlord must pay the resident £175 made up as follows:
This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date. The landlord can deduct any amount it has already paid. |
No later than 05 May 2026 |
|
3 |
Communication order The landlord must write to the resident to confirm the current status of the stopcock. The letter must clearly state:
The landlord must provide us with a copy of this letter. |
No later than 05 May 2026 |
Our investigation
The complaint procedure
|
Date |
What happened |
|
2 August 2024 |
The resident contacted the landlord to complain. In summary, she said:
|
|
7 August 2024 |
The landlord acknowledged the resident’s complaint and said it aimed to provide its stage 1 response within 10 working days |
|
14 August 2024 |
The landlord issued its stage 1 response. In summary, it said:
|
|
20 August 2024 |
The resident contacted the landlord to explain that the stopcock was still leaking and that the problem remained unresolved. She said the leak continued, and she sent a video to show this. In summary, she said:
|
|
20 August 2024 |
The landlord acknowledged the resident’s escalation and said it aimed to provide its stage 2 response within 20 working days |
|
11 September 2024 |
The landlord issued its stage 2 response. In summary, it said:
|
|
Referral to the Ombudsman |
The resident brought the complaint to us saying the stopcock repair still remained outstanding. In summary, she said:
The resident told us in a recent conversation that the landlord has still not replaced the stopcock and she worries this might be an issue soon. |
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
The landlord’s handling of the repair to the stopcock |
|
Finding |
Service failure |
- The landlord’s repairs policy said it was responsible for the structure of the building. It set clear targets: attend emergency repairs the same day, complete urgent repairs within 3–5 working days, and complete routine repairs within 20 working days.
- The resident reported a leaking stopcock on 24 June 2024. The landlord arranged an appointment for 25 June 2024 and sent a heating contractor, who said the job needed a plumber. Sending the wrong contractor meant the repair could not progress and caused a wasted visit.
- The contractor told the landlord the same day that a plumber was needed. The landlord raised a new repair on 2 July 2024 and attended on 22 July 2024, which was within its 20‑day routine repair target and in line with its policy. During this visit, it found the stopcock was leaking, hard to control and needed replacing.
- On 25 July 2024 the landlord told the resident that plumbing works would take place on 2 August 2024 and that it would need to turn off the water to the block. This communication was clear.
- The landlord attended on 2 August 2024. It explained the plumber could not replace the stopcock because its position and the surrounding pipework made the work unsafe. The plumber repacked the gland to reduce the leak and said further work was needed. However, the landlord had already inspected the stopcock on 22 July 2024. It is unclear why the earlier visit did not identify the same issue with the pipework.
- The landlord attended again on 22 August 2024 to repair the stopcock, which left it working. Given the landlord already knew a replacement was needed, and had already attended to repair it, it is not clear why this extra visit was required. The full repair took 43 working days from 24 June 2024 to 22 August 2024, which was outside the landlord’s 20‑day timescale for routine repairs and therefore not in line with its repairs policy.
- The landlord’s stage 2 response showed it had carried out a thorough review of the repair issues. It explained what had happened, identified where the repairs had gone wrong, apologised for the poor service, and recognised the time and trouble the resident experienced. It also offered £100, which was reasonable and in line with our remedy guidance and its own compensation policy.
- However, the repair notes of 22 August 2024, as referenced in the landlord’s final response, said a contractor was needed to replace the stopcock or to get the stopcocks by the tanks working. It was not clear whether this referred to the same stopcock or a different one. The landlord first identified on 22 July 2024 that the stopcock required replacement, and 20 months later, in March 2026, the resident said it had still not been replaced.
- Landlords are required under the Landlord and Tenant Act 1985 to keep installations in repair and in good working condition. The landlord is expected to repair items where a repair is possible and effective. However, where a part is beyond economical repair or cannot be restored to a reliable working condition, the landlord can recommend or carry out a replacement. Earlier notes in this case suggested a replacement, however it repaired and left the stopcock in a working condition.
- The landlord should have clarified in its final response whether the stopcock still required replacement or whether the works on 22 August 2024 had fully resolved the issue. If replacement was still needed, it should have set out the next steps or committed to providing a timeline. The stage 2 response did not do this, which left the resident without clarity about the outstanding repair and meant she had to keep chasing the landlord for updates, causing avoidable time and inconvenience.
|
Complaint |
The handling of the complaint |
|
Finding |
No maladministration |
- Our Complaint Handling Code (the Code) sets out when and how a landlord should respond to complaints. The relevant code in this case was the 2024 edition. At the time of the complaint, the landlord’s policy was compliant with the Code.
- At both stages of the complaint, it says the landlord would acknowledge within 5 working days, provide its stage 1 response within 10 working days and provide its stage 2 response within 20 working days.
- The landlord acknowledged the complaint 3 working days later (2 August 2024 to 7 August 2024) and provided its stage 1 response on 14 August 2024, 5 working days from its acknowledgement. This was in line with its policy and the Code.
- It acknowledged the resident’s escalation the same day on 20 August 2024 and provided its stage 2 response 16 working days after the acknowledgement (20 August 2024 to 11 September 2024). This was in line with its policy and the Code.
Learning
Knowledge information management (record keeping)
- The landlord should improve its record‑keeping on repairs so it has the information they need when residents call. In this case, gaps in the repair records meant the resident was asked to contact the contractor directly. This placed the burden on the resident and led to avoidable time and trouble to the resident.
Communication
- The landlord should review how it manages appointment text messages. In this case, the resident received texts saying access was needed even for communal works. This caused confusion and unnecessary time at home. The landlord could consider making its messages clear if access is required.