Aster Group Limited (202403154)

Back to Top

 

Decision

Case ID

202403154

Decision type

Investigation

Landlord

Aster Group Limited

Landlord type

Housing Association

Occupancy

Shared Ownership

Date

17 April 2026

 

Background

  1. The resident’s front door was painted on 29 November 2022 as part of a major works programme. The landlord later accepted that the work did not meet an adequate standard and the door needed to be repainted. In March 2024 the resident complained that the repainting remained incomplete and that the landlord had not taken their access related requests and concerns into account.

 

What the complaint is about

  1. The complaint is about the landlord’s handling of:
    1. Repainting the resident’s front door.
    2. The associated complaint.

 

Our decision (determination)

  1. We have found maladministration in the landlord’s handling of repainting the front door.
  2. We have found service failure in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

 

Summary of reasons

Repainting the front door.

  1. The landlord’s approach to arranging access for the works was not sufficiently proactive. It did not effectively coordinate with both the resident and the contractor before considering legal action.

Complaint handling.

  1. The landlord did not respond within its policy timescales and did not provide a full response at stage 1.

 

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

 

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is made by a senior staff member.
  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

18 May 2026

2

Compensation order

The landlord must pay total compensation of £250 as follows:

  1. £200 in recognition of the delays, distress and inconvenience caused by its handling of repainting the front door.
  2. £50 for its complaint handling failures.

This must be paid directly to the resident by the due date. The

landlord must provide documentary evidence of payment by the due

date.

No later than

18 May 2026

 

Our investigation

The complaint procedure

Date

What happened

20 March 2024

The resident raised a complaint about access arrangements for repainting their front door. They said:

  • The contractor had not painted the door to an acceptable standard despite repeated requests for highquality refurbishment.
  • The landlord knew their work schedule but continued to request weekday access during business hours, or confirmation that someone else could provide access.
  • Their home insurance would be invalid if they left their flat unlocked.
  • A previous appointment during major works had resulted in their home being left in an unacceptable condition.
  • They felt pressured to take unpaid leave to provide access for a correction that should have been completed properly the first time.

12 April 2024

The landlord apologised for its delay in responding. It said it had hoped to respond by 12 April 2024, but now expected to reply by 26 April 2024.

21 April 2024

The resident expressed concerns about the landlord’s complaint handling. They said:

  • They had not received a voicemail or phone contact from the complaint handler.
  • They originally complained because they felt pressured to stay home unpaid to provide access, which was difficult due to their care work and concerns about leaving the door open.
  • Their lease requires “reasonable” access but not strict weekday availability.
  • They had attempted to arrange leave with their employer until they became aware of an email dated 4 April 2024. The email had been sent to their neighbour rather than them, stating they must provide access during business hours and warning of possible legal action. As a result, they wished to add the landlord’s threat of legal action to their complaint.
  • They had received no communication about the door from 7 December 2023 to 11 March 2024.
  • The contractor had since agreed to a Saturday appointment and they questioned why this option had not been explored before legal action was raised.

26 April 2024

The landlord issued its stage 1 response. It:

  • Said poor phone signal had made communication difficult.
  • Acknowledged that the resident had struggled to take leave to provide access.
  • Accepted that the resident wanted the door repainted to a proper standard without financial loss.
  • Apologised that the door had been painted shut and said action was taken at the time, including removing the painters from the site.
  • Said its contractor had tried to arrange an appointment but had not received a response.
  • Said it had confirmed that the contractor would attend on a Saturday as an exception as an evening appointment was unsuitable due to drying time.

2 May 2024

The resident escalated their complaint. They said the stage 1 response had not addressed their concerns about threats of legal action. They also disputed that the complaint handler had initiated contact with the contractor.

5 June 2024

The landlord issued its stage 2 response. It:

  • Accepted the resident wanted the door decorated to an appropriate standard.
  • Confirmed the door was repainted on Saturday 11 May 2024.
  • Acknowledged the resident’s frustration with delays but said access difficulties had contributed.
  • Apologised if the email referring to legal action for no access had caused upset but said it was following its procedure, which could include injunctions.
  • Did not uphold the complaint, stating a Saturday appointment had been the most practical solution.

Referral to the Ombudsman

On 9 July 2024 the resident asked us to investigate their complaint. They said they felt that the landlord had not listened to them and should have apologised and offered compensation.

 

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of repainting the resident’s front door.

Finding

Maladministration

  1. The resident’s door was painted during a programme of major works on 29 November 2022. The resident advised that the door was painted shut while they were out and they had to force the door to get into their flat.
  2. The door repainting issue took place within a wider dispute between residents and the landlord about service charges and the quality of major works. A case was also brought to the First Tier Tribunal (FTT). At the hearing on 21 November 2023, the landlord acknowledged that the resident’s front door had not been painted to an acceptable standard. The FTT directed the landlord to repaint the resident’s front door to their satisfaction as soon as possible.
  3. Following the FTT determination, the landlord’s contractor contacted the resident by text message on 7 December 2023. It asked to arrange a day for the door to be repainted. The landlord said that the resident did not respond. The resident disputes this. They have told us the contractor was on site at the time and they spoke to them directly about a date, but nothing happened. They said they were not contacted again until 11 March 2024. It is positive that the landlord took steps to make an appointment. However, we do not consider that a single text message was sufficient, particularly in the context of the FTT decision and it could have followed up sooner.
  4. The resident’s lease requires them to provide reasonable access for works. It was reasonable for the landlord to request access during standard business hours. However, raising the possibility of legal action without first exploring alternative access arrangements, including out-of-hours options, was disproportionate. The resident reported that the threat of legal action caused them distress and they did not believe the landlord had listened to their needs regarding access arrangements. The possibility of legal action was also communicated to the resident’s neighbour rather than to the resident directly. If the landlord intended to consider legal proceedings, it should have informed the resident directly and transparently.
  5. In its stage 2 response, the landlord stated it had followed procedure due to continued no-access and that pursuing an injunction was sometimes necessary. However, this is inconsistent with the landlord’s later confirmation to us on 1 April 2026 that its no-access procedure was not introduced until June 2025. The information provided to the resident in 2024 that it was acting in accordance with established procedure was therefore incorrect.
  6. The door was repainted on Saturday 11 May 2024. It is clear there were difficulties with arranging suitable access and it is positive that the landlord’s contractor agreed to work outside of its usual operating hours. However, the landlord could have contacted the resident sooner and explored reasonable alternative arrangements before escalating to discussing potential legal action.
  7. We therefore find maladministration in the landlord’s handling of repainting the front door. We have ordered it to apologise and pay £200 in compensation to reflect the delays in repainting the door and the distress caused to the resident by the threat of legal action.

Complaint

The landlord’s handling of the complaint.

Finding

Service failure

  1. The landlord’s complaints policy stated it would provide a stage 1 response within 10 working days and would not exceed a further 10 days without good reason. It would provide a stage 2 response within 20 working days and would not exceed a further 20 days without good reason.
  2. The landlord issued its stage 1 response after 26 working days, which exceeded its policy timescales.
  3. Our Complaint Handling Code requires landlords to address all issues raised, including related matters added before the stage 1 response is issued. The resident raised their concerns about the threat of legal action before the landlord issued its stage 1 response. The landlord should therefore have addressed the resident’s concerns about legal action at stage 1.
  4. The landlord issued its stage 2 response after 23 working days, which is slightly outside of its policy timescales.
  5. The landlord apologised for the delay at stage 1 of its complaints process. However, both complaint responses were issued late, and the landlord failed to address the resident’s concerns about the threat of legal action at stage 1. The resident had also made it clear that they found the prospect of legal action distressing. By omitting any reference to legal action in its stage 1 response, the landlord missed an opportunity to acknowledge and respond to these concerns at an earlier stage. We have therefore found service failure in the landlord’s handling of the complaint.
  6. We have ordered the landlord to apologise and pay £50 compensation for the complaint handling failures identified in this report.

Learning

  1. The landlord should have ensured that any reference to legal action was proportionate and that the information provided to the resident about its procedures accurately reflected the processes in place at the time. It is positive that the landlord has since introduced a formal no-access procedure.

Knowledge information management (record keeping)

  1. There were gaps in the landlord’s records about when the door was first painted and when further works orders were raised. The landlord may wish to review its record keeping for major works.

Communication

  1. The landlord’s communication could be improved. In this case, the landlord should have taken a more proactive and coordinated approach to arranging access, ensuring timely follow‑ups and early exploration of reasonable alternatives.