Peabody Trust (202343735)
|
Decision |
|
|
Case ID |
202343735 |
|
Decision type |
Investigation |
|
Landlord |
Peabody Trust |
|
Landlord type |
Housing Association |
|
Occupancy |
Leaseholder |
|
Date |
31 March 2026 |
Background
- The leaseholder rents out the flat. He reported water entering the 3 bedrooms at the back of the flat and said he could see that the guttering was leaking. He made a formal complaint because the landlord did not carry out the repair. He later asked the landlord to reimburse him for the direct expenses he incurred when he arranged the repair himself.
What the complaint is about
- The leaseholder’s complaint is about the landlord’s handling of:
- Repairs to the guttering.
- The associated complaint.
Our decision (determination)
- We found the landlord responsible for maladministration in its handling of repairs to the guttering.
- We found the landlord made an offer of reasonable redress which resolved its complaint handling failings.
We have made orders for the landlord to put things right.
Summary of reasons
The landlord’s handling of repairs to the guttering
- The landlord failed to repair the guttering despite repeated reports of water ingress. It relied on incorrect contractor evidence from a different property and continued to say repairs were complete even though the leak persisted and the leaseholder repeatedly provided evidence to the contrary. As a result, the leaseholder told the landlord he would arrange the works himself. The landlord did not reply to this, and he then arranged and funded the work himself.
The landlord’s handling of the associated complaint
- The landlord significantly delayed acknowledging and responding to the leaseholder’s complaint at both stages of the process. However, it recognised these failings, apologised, and offered £300 in compensation. This offer is reasonable to put things right by recognising the time and trouble caused by the complaint handling delays.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order The landlord must apologise in writing to the leaseholder for the failures identified in this report. The landlord must ensure:
|
No later than 28 April 2026 |
|
2 |
Compensation order The landlord must pay the leaseholder £8,934 (including the £2,150 already offered – £1,800 at stage 2 and £350 offered at stage 1 towards the insurance excess) made up as follows:
|
No later than 28 April 2026 |
|
3 |
Learning order The landlord must carry out a senior management review of the failures identified in this case and produce a report detailing its learning. The review should include, but is not limited to:
The report should outline the steps the landlord will take to make sure these failings are not repeated in the future. The landlord must provide a copy of its report to us within 6 weeks of the date of this decision. |
No later than 12 May 2026 |
Recommendation
Our recommendations are not binding, and a landlord may decide not to follow them.
|
Our recommendation |
|
We recommend that the landlord pay £300 in compensation that it offered in its stage 2 response for the time and trouble caused by complaints handling failures. |
Our investigation
The complaint procedure
|
Date |
What happened |
|
9 October 2023 |
The leaseholder raised a formal complaint online. He said:
|
|
13 November 2023 |
The leaseholder raised another formal complaint online. He said:
|
|
25 November 2023 |
The leaseholder obtained a quote for the work totalling £9,000, made up of:
|
|
16 December 2023 |
The leaseholder raised a further formal complaint online. He said:
|
|
15 January 2024 |
The landlord issued its stage 1 response (dated 8 January 2024 but emailed on 15 January). It said:
|
|
15 January 2024 |
The leaseholder escalated his complaint. He said:
|
|
January to February 2024 |
The landlord’s liability insurer rejected the leaseholder’s claim for reimbursement. It told the landlord’s complaints team that guttering repairs were the landlord’s responsibility and therefore not covered under the liability insurance policy. |
|
16 April 2024 |
The landlord issued its stage 2 response. It said:
|
|
Referral to the Ombudsman |
The leaseholder brought the complaint to us because he was not satisfied with the landlord’s response. He wanted:
|
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
The landlord’s handling of repairs to the guttering |
|
Finding |
Maladministration |
- Under the lease, the landlord is responsible for maintaining and repairing the external parts of the building, which includes the guttering. The leaseholder’s flat is on the first floor. There are 3 bedrooms at the back of the flat with guttering for the building located directly above the flat.
- The leaseholder reported water ingress into the 3 bedrooms in September 2023 and provided photos showing leaking guttering. The landlord initially raised the repair to the wrong property on 3 separate occasions, causing around 2 weeks delay and requiring the leaseholder to chase repeatedly.
- On 1 October 2023, the landlord raised a job with a contractor for the correct property. The contractor reported that works were completed by 26 October 2023. However, the contractor’s photographs showed a different property with a different guttering system. In November 2023, after the landlord said the repair was completed, the leaseholder told the landlord that the description of a ‘missing hopper’ did not match the design of the guttering on his building. He asked to speak to the contractor and to meet the landlord or contractor at the property to show them the problem. Despite this, the landlord continued to state, in both its January and April 2024 complaint responses, that the contractor had attended and completed a repair. The photos from the job were later shared with the leaseholder, who confirmed he does not own the property where the works were carried out.
- Following the contractor’s reported visit, the leaseholder continued to report the issue persisted, and he provided further evidence. He told the landlord that:
- The water ingress continued.
- The bedrooms were no longer useable.
- Internal damage was worsening.
- His tenants had contacted the Council’s Environmental Health Department due to the conditions.
- On 13 November 2023, the leaseholder submitted a complaint stating he may need to employ his own contractor if the landlord did not act. Over the following weeks, he repeatedly emailed and called the landlord explaining that he felt he had no option but to arrange the works himself. He obtained a £9,000 quote on 25 November 2023 and sent it to the landlord on 30 November 2023. The landlord did not give a clear response on whether it agreed to him arranging his own repair or whether it would reimburse the costs, instead either not responding or advising that someone would get back to him. In its complaint responses, the landlord later said it does not reimburse customers who employ contractors without written permission in advance, which is generally a reasonable position. However, in this case the leaseholder gave notice of his intention and sought permission, and the landlord missed the opportunity to set out its position before the works proceeded.
- The leaseholder’s contractor completed the works by 8 December 2023, after which the water ingress stopped. The leaseholder then submitted the invoice and requested reimbursement. The landlord advised him to submit a liability insurance claim which was later rejected because guttering repairs were the landlord’s responsibility and therefore not covered under the liability policy. The landlord then refused reimbursement on the basis that it had not approved the works in advance and continued to rely on the contractor’s incorrect October 2023 attendance report to confirm that it had done the work needed.
- Overall, there was maladministration in the landlord’s handling of the guttering repairs. The landlord did not resolve the issue, repeatedly maintained the works had been completed at the correct property when they had not, and failed to take action despite clear and escalating evidence of worsening water ingress. As a result, the leaseholder felt he had no choice but to arrange the repairs himself. This had a significant impact as he:
- Paid the full cost of the external works.
- Spent considerable time chasing the landlord.
- Was concerned about potential enforcement action from Environmental Health.
- While the landlord offered £1,000 as a goodwill contribution towards the repair costs, this does not reflect the nature or extent of the landlord’s failings. The building contains 6 flats, and the leaseholder is responsible for 16.67% of external repair costs via service charges. Given the circumstances of this case, it is fair and reasonable for the landlord to reimburse £7,500 (83.33% of the repair cost). This is because the landlord had the opportunity to repair the guttering but failed to do so; it incorrectly accepted that repairs had been completed despite evidence to the contrary; and it did not clarify its position during the 3-week period when the leaseholder warned it he would proceed independently.
- The leaseholder asked for interest of 45% per annum on the loan he took out at the beginning of December 2023 to fund the repairs. The Ombudsman can consider ordering compensation to recognise the loss of interest (based on the Consumer Price Index) where a landlord has not paid money due to a leaseholder, the financial loss exceeds £1,000, and the period involved is more than 6 months. In this case, the leaseholder chose to fund the repair by taking out a personal loan for £9,000 and the level of interest charged arose from his chosen method of borrowing. It would therefore not be fair or proportionate to require the landlord to pay interest at a rate of 45%. The Consumer Price Index from 1 June 2024 (6 months after the leaseholder paid for the work) to 31 March 2026 (a 22- month period) averaged 3.54% per annum. In our view, it is fair and reasonable for the landlord to pay £584 in interest, based on applying a 3.54% CPI rate to £9,000 over 22 months.
- In its stage 1 response, the landlord offered £350 towards the building insurance excess for internal damage. This was not included in the stage 2 response. The leaseholder asked for the full £500 excess to be reimbursed. We find that £350 is fair and reasonable, as some of the damage was likely caused by the initial water ingress, though the delays contributed to it worsening. We have therefore made an order for the landlord to pay this amount.
- The landlord offered £500 compensation for distress and inconvenience. This is in line with our remedies guidance where maladministration has adversely affected a leaseholder. We find the amount fair and reasonable.
|
Complaint |
The handling of the complaint |
|
Finding |
Reasonable redress |
- The landlord’s policy defines a complaint as an expression of dissatisfaction about the standard of service, actions, or lack of action by the organisation. The policy says it will acknowledge complaints within 5 working days, issue a stage 1 response within 10 working days, and a stage 2 response within 20 working days. If additional time is needed, the landlord may extend these deadlines by up to 10 working days at stage 1 and 20 working days at stage 2, provided it informs the customer.
- The leaseholder expressed dissatisfaction several times and through multiple channels, beginning with an online complaint on 9 October 2023. He continued to express dissatisfaction through further online complaint forms, calls, emails, and social media. Despite this, the landlord did not acknowledge his complaint until 16 December 2023, after his third attempt to submit a complaint via the webform. This delay of more than 2 months was not reasonable and fell significantly outside the landlord’s 5-day acknowledgement timeframe.
- The leaseholder escalated his complaint to stage 2 on 15 January 2024. The landlord acknowledged this 3 days late. It was then delayed in allocating the case, meaning the response deadline of 22 February 2024 was missed. The leaseholder and this Service chased for a stage 2 response. On 4 March 2024, the landlord said it needed a further 10 working days to respond and then issued its stage 2 response on 16 April 2024.
- There were significant delays in the landlord’s complaints handling. In its stage 2 response, it acknowledged and apologised for this. It offered £300 in compensation for its complaint handling failures. We agree this amount is fair and reasonable to recognise the time and trouble caused to the leaseholder from the complaint handling delays. Our finding of reasonable redress is dependent on the landlord making this payment.
Learning
- There is significant learning that the landlord can take from this investigation. Responding promptly when a leaseholder indicates they may take independent action, such as hiring their own contractor, may help to avoid disputes about liability, costs, or reimbursement expectations.
Knowledge information management (record keeping)
- Ensuring that repair instructions and contractor reports are checked for accuracy, especially where residents or leaseholders provide contradictory evidence, may help avoid situations where incorrect works are accepted as completed.
Communication
- The communication with the leaseholder was poor. He did not receive meaningful responses that addressed his questions or considered the evidence he provided. Despite asking, he was not given the opportunity to speak with the contractor about the problem. This could have provided a quicker resolution as it would have been an opportunity to clear up the confusion about which property had been visited.