London Borough of Newham (202451567)

Back to Top

Decision

Case ID

202451567

Decision type

Investigation

Landlord

London Borough of Newham

Landlord type

Local Authority / ALMO or TMO

Occupancy

Secure Tenancy

Date

12 May 2026

Background

  1. The property is a 2-bed flat on the second floor in a block of flats. The resident reported longstanding issues with the water pressure in the property on 12 April 2023, stating that this was making it very difficult for her and her family to wash. The landlord first completed works to replace pipes and repair a leaking stopcock in August and September 2023, but the issue persisted throughout the block. After advising the resident that it believed this was the water supplier’s responsibility to repair, the landlord later coordinated with them to identify the source of the issue. The water supplier completed works to resolve the issue on 27 November 2025.

What the complaint is about

  1. The landlord’s handling of the resident’s reports of low water pressure.
  2. We have also considered the landlord’s complaint handling.

Our decision (determination)

  1. There was maladministration in the landlord’s handling of the resident’s reports of low water pressure.
  2. There was severe maladministration in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

The landlord’s handling of the resident’s reports of low water pressure

  1. The landlord did not carry out the works to replace pipes and repair the leaking stopcock within its timescales. It did not follow up on a plan to install a water pressure booster pump, and did not communicate with the resident any alternate plans it had to progress the repairs. There were significant delays before the landlord worked with the water supplier to find a resolution after its stage 2 response. The landlord did not fully acknowledge the impact of this repair on the ability of the resident and her family to wash and bathe. As such the compensation was not sufficient to put things right. 

 

The landlord’s handling of the complaint

  1. There were considerable delays in the complaint progressing at both stage 1 and stage 2. While it acknowledged stage 2 delays and offered compensation, it did not acknowledge the delays at stage 1. The landlord failed to identify 4 reasonable requests to escalate the complaint to stage 2, contributing to the delays. The landlord could not demonstrate learning and its compensation was not sufficient to put things right.

 


Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. Given the finding of severe maladministration for complaint handling, the apology must come from its interim Chief Executive. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

10 June 2026

2

Compensation order

The landlord must pay the resident a total of £1,000 compensation, made up of:

 £750 for the impact of the landlord’s handling of low water pressure.

 £250 for the impact of the landlord’s complaint handling.

This is inclusive of what the landlord offered during its process, and the landlord may wish to deduct the £600 it has already paid to the resident.

This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date.

No later than 10 June 2026

3

Case Review order

The landlord is to complete a case review both of its handling of the issues with water pressure, and of the complaint in general. The review must be completed by a senior member of its staff and a copy must be provided to us.  The review should include the delays in both the works being completed, and the complaint progressing through the landlord’s procedure. It should also include its communication and its oversight of the repairs. The review should also aim to identify improvements in relation to processes and staff training where necessary.

No later than 10 June 2026

 

Recommendations

Our recommendations are not binding, and a landlord may decide not to follow them.

Our recommendations

The landlord should consider carrying out a review of the impact the water pressure issue had on other neighbouring residents in the block.


 


Our investigation

The complaint procedure

Date

What happened

12 April 2023

The resident raised a complaint about 2 different issues by email:

 

  • The latter of these was about very low, sometimes non-existent water pressure, which she said she had been reporting over the previous year.

 

21 April 2023

The landlord issued a stage 1 response under its reference 22541361 about these different issues. Regarding the water pressure- it said that it had responded to the resident’s report on 12 April 2023 by raising an emergency job to make safe, and that a future appointment had been made for follow-up repairs.

 

Later that day the resident responded to say that:

 

  • She was unhappy with this, and that the landlord had not said anything about the water pressure issue.

5 May 2023

The landlord issued another stage 1 response under its reference 22710730:

 

  • The landlord apologised for delays in the repairs being resolved, including the water pressure.
  • It also acknowledged the impact this was having on the resident and her household.
  • It said that an outstanding list of repairs had been passed to a complaints manager and repairs manager, and that a surveyor had been tasked to carry out a full inspection including the water pressure and taps.

31 July 2023

The resident contacted the landlord again to complain about ongoing issues with the water pressure:

 

  • She complained that the landlord had not attended to the property until her MP had become involved.
  • She described how she had to use water from the kettle to run a bath, and that she had to buy large amounts of bottled water to fill the kettle. She also said that it took hours to complete tasks like washing hair, dishes, and clothes. 

3 August 2023

The landlord issued a third stage 1 response regarding the water pressure under its reference 25225108. It said that:

 

  • It said that a repair for water pressure had not previously been raised.
  • A repair had been raised that day, and was appointed for 4 September 2023.

9 August 2023

The resident contacted the landlord to dispute what it had written in its stage 1 response of 3 August 2023. She said that she had reported the issue with the water pressure before, and that there was evidence of this (both that her MP had already contacted the landlord about the issue, and that a member of staff had already carried out an inspection).

19 October 2023

The landlord sent out a fourth stage 1 response under its reference 25508694. It said that:

 

  • The repair appointed for 04 September 2023 (mentioned in the previous stage 1 response) was recorded as no-access. 
  • A leaking stopcock was repaired on 28 September 2023, and on the day afterwards it was found that the fault was with the mains supply.
  • It said that the resident had informed the landlord that the water supplier had told her that the fault was with the upper level pipework, which was the landlord’s responsibility to maintain.
  • The landlord would look into whether a water pressure booster could be fitted, and that contractor would contact the resident direct about this.

 

6 November 2023

The resident emailed the landlord to say that:

 

  • She said she was unhappy that her MP had been told that contractors had told her to get in touch with the water supplier as a means of resolving this. She said no-one had contacted her, and maintained that this water supplier was telling her that it was the landlord’s responsibility to repair.
  • She said that pipes were still leaking, and that she was still living without a water supply.

18 November 2024

The resident again contacted the landlord, this time explicitly saying that she wanted the complaint to be escalated to stage 2:

 

  • She said that a representative from the water supplier had attended and recommended that the landlord install a water booster pump system to improve pressure throughout the block.

 

14 February 2025

The landlord issued its stage 2 response. It said that:

 

  • It had not followed up on a request from January 2024 for quotes for a water pressure booster pump. Quotes had now been received for this pump, and the resident would be contacted with a start date for repairs by 24 February 2025.
  • It acknowledged that the stage 2 response had not been issued within its timescales, and offered £50 compensation for this.
  • It awarded a further £550 compensation, broken down as £400 for delays in the works being completed, and £150 for the resident’s time and trouble in chasing the water pressure repairs.

Referral to the Ombudsman

When referring the complaint to our service, the resident said that:

 

  • Water pressure booster pumps were not fitted following the stage 2 response.
  • Until the issue was resolved in late 2025, the water pressure would fluctuate wildly throughout the day, making it extremely difficult to plan when she and her family could bathe. She said that this had an impact on her mental health, and on the physical health of her daughter. 
  • While the resident had been paid the £600 offered by the landlord, she remained unhappy with this as a total level of compensation.

 


What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of the resident’s reports of issues with water pressure

Finding

Maladministration

What we have not considered

  1. The resident reported that both her and her daughter’s health had been negatively impacted by this issue. We do not doubt the resident’s comments, however it is not within our remit and expertise to determine causation, liability, or the impact on a resident’s health. Such matters are more appropriately addressed through the courts.
  2. We are aware that the resident said she had been reporting issues with the water pressure for several years before 12 April 2023, but we have not seen any reports of this earlier than their first complaint of the same date. While we do not doubt these historical reports occurred we have to work with the evidence we have to hand, and we expect residents to raise a complaint within a reasonable time of an issue becoming apparent. Therefore we have considered in this investigation events from 12 April 2023 onwards.

What we have considered

  1. The landlord accepted repair responsibility (as set out in the tenancy agreement) for the maintenance of communal areas including external pipes, as well as installations for the supply of water.
  2. The landlord’s repairs policy explains that it will attend to and complete repairs deemed urgent between 3 and 7 calendar days, and more routine works will be attended to within 20 working days.
  3. The landlord’s compensation policy (the version provided for this investigation) says that the landlord may consider compensation for continuing loss of amenity, including difficulties in being able to wash. As early as 25 May 2023 the resident’s MP wrote to the landlord and described the impact on the resident’s family, namely, that it took several hours to be able to shower, and that water would abruptly shut off. Our investigation period shows that the resident and her family were intermittently impacted by this for over 2 years.
  4. Both of the first 2 stage 1 responses (21 April 2023 and 5 May 2023) lacked detail on how the landlord planned to respond to this repair issue. The first said that an emergency job had been attended to, and a follow-on repair had been booked, but we cannot see any evidence of this further repair. The second said that a list of outstanding repairs had been passed to management to monitor, and that a surveyor would carry out an inspection. We cannot see what specific repairs these are, and again there is no evidence of these repairs being booked or attended to around this time, though the resident confirmed that an inspection did take place in early June 2023.
  5. Following this, the landlord emailed a contractor on 8 June 2023, asking it to test, trace and rectify the source of low water pressure. These works were confirmed to be completed on 23 August 2023 which, at 92 working days after the resident’s first report, is significantly outside of the landlord’s timescales to attend to routine repairs.
  6. The third stage 1 response (3 August 2023) erroneously said that low water pressure had not been raised as a repair. However, by this point the resident had already reported this, and her MP had also raised this with the landlord. We can also see that the landlord had already inspected the property, and raised works with contractors specifically for low water pressure. This oversight meant that the landlord missed a chance to identify a way to resolve these repairs, and also showed issues with its record keeping. This caused additional frustration to the resident.
  7. The landlord’s fourth stage 1 response on 19 October 2023 acknowledged that the works completed in August and September had not resolved the issue, and that it would look into whether a water pressure booster pump could be fitted. At stage 2, which was issued 14 months later, it acknowledged that this had never been followed up on, and said that orders would be soon raised for this. The resident continued to chase this for the next 2 months, and there is no evidence that this pump was ever fitted.
  8. This may be because the landlord later decided on a different course of action, and we see that it did complete alternate works in October 2025. However, good customer service requires it to keep in contact and provide updates on the progress of works, particularly when they are complex and require further investigation and time. There is no evidence the landlord did so from February to November 2025.
  9. It is clear that throughout the complaint there were questions over whether the landlord or the water supplier was responsible for resolving this issue. As early as 25 May 2023 the resident’s MP highlighted this, and asked if the landlord could coordinate with the water supplier to try and find a solution. While it was the water supplier that completed works to resolve the issue on 27 November 2025, it was reasonable to expect that the landlord take a role in coordinating with another body who may have been responsible for a repair impacting its properties. From the evidence submitted we cannot see that this happened until September 2025, which is 28 months after it was first requested to so do.
  10. At stage 2 the landlord acknowledged the delays and offered £550 compensation both for delays in the works being done, and the resident’s trouble in chasing the repairs. However, it could not demonstrate that it had taken any learning as it did not improve its communication with the resident after stage 2 response was issued. It also did not effectively communicate with the water supplier in a timely manner.
  11. The overall compensation did not go far enough to account for the failings in communication, and the time the repairs remained outstanding. As already stated above, it failed to assess whether this led to the loss of the ability for the resident and her family to wash. However, this reportedly impacted their use of the property. In line with our compensation guidance have ordered a total of £750 compensation (including the landlord’s offer of £550) to reflect both the length of time the resident was adversely impacted by this, and the severity of this impact.

Complaint

The handling of the complaint

Finding

Severe maladministration

  1. The Code in place (at the time of the complaint being considered at stage 1) required landlords to issue a stage 1 response within 10 working days of a complaint being logged, and to issue a stage 2 response within 20 working days of a complaint being escalated. Later during the landlord’s consideration at stage 2 our Code had been updated to give landlords an additional 5 working days to acknowledge a complaint at stage 2.
  2. The Code that was in place in 2023 also made clear that if all or part of a complaint was not resolved to the resident’s satisfaction at stage 1, then it must be progressed to stage 2 of the landlord’s procedure. The landlord’s housing complaints policy confirmed that if a resident does not agree with a stage 1 response then it should be escalated to stage 2.
  3. The resident first raised the issue of water pressure within a complaint on 12 April 2023. While the landlord did mention this in its stage 1 response of 21 April, it did not make clear whether it was treating the water pressure issue as a first time service request or a complaint. As the landlord did not clarify this, it was understandable that the resident considered its response to the issue as a complaint response.
  4. She expressed her dissatisfaction with the response on 21 April, the same day as the first stage 1 response. The landlord should have either treated this as an escalation request, or explained why it raised another stage 1 complaint for the same issue. However, the landlord did not do any of this, and instead sent out another stage 1 response on 5 May 2023.
  5. There were further expressions of dissatisfaction which led the landlord to send out a further 2 stage 1 responses, making a total of 4 stage 1 responses being provided for the same issue. The last stage 1 response was issued in October 2023, after considerable delays. This caused both confusion about the landlord’s complaint process, and avoidable delays. This serious failure meant that the resident was prevented from exhausting the landlord’s process and bringing her complaint to us at an earlier stage. It also inconvenienced the resident as she had to involve her MP to assist with chasing this issue.
  6. Following the landlord’s fourth stage 1 response, the resident contacted its complaints team inbox on 6 November 2023 where she reported that the water pressure problems were ongoing, and that there were still leaks from pipes. Much like the earlier instances of her dissatisfaction as referred above, this email should have been treated as an escalation request as it was clear that the complaint had not been resolved for the resident. However, the landlord did not escalate her complaint until November 2024 after the resident explicitly said that she wanted it to be escalated to stage 2. These further failings meant that the complaint took considerable time to exhaust the landlord’s process, with a total of 457 working days at both stages.
  7. The landlord missed opportunities to demonstrate learning as it only identified failings in its complaint handling at stage 2, and its offer of £50 for failings at stage 2 was insufficient. In addition to the learning order, and in line with our compensation guidance we have ordered £250 compensation to reflect the lengthy delays at both stage 1 and stage 2, and the significant errors in the landlord’s application of the Code, and its own complaints policy.

Learning

  1. We have asked the landlord to complete a learning review. The landlord failed to retain an oversight over its contractors and procedures to ensure that it could meet its repair timescales. In particular when raising repairs, coordinating with another stakeholder, and updating residents on the progress of repairs. The landlord needs to know why these failures occurred.

Knowledge information management (record keeping)

  1. The landlord could not evidence all the repair appointments it referred to in its complaint responses. Additionally, its information management affected its response and led to incorrect statements that the resident had not reported the water pressure.

Communication

  1. Outside of the stage 1 and stage 2 complaint responses, there is no evidence of the landlord keeping the resident updated on the progress of repairs and reasons for delays with both the substantive issue and its complaint handling. This continued for several months after the complaints procedure was exhausted.