Orbit Housing Association Limited (202441912)

Back to Top

 

Decision

Case ID

202441912

Decision type

Investigation

Landlord

Orbit Housing Association Limited

Landlord type

Housing Association

Occupancy

Assured Tenancy

Date

10 February 2026

Background

  1. The resident complained that the landlord failed to address her reports of damp and mould for several years. The landlord investigated her complaint and acknowledged delays from 2020 onwards. It offered compensation and committed to a schedule of works to address damp and mould throughout the property. The resident complained it then failed to complete these works.

What the complaint is about

  1. The complaint is about how the landlord handled works to address damp and mould.
  2. We have also considered the landlord’s complaint handling.

Our decision (determination)

  1. We found that:
    1. There was maladministration in:
      1. How the landlord handled works to address damp and mould.
      2. The landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

  1. The landlord failed to complete the works committed to in its final complaint response within a reasonable timeframe.
  2. The landlord exceeded its stage 2 complaint response timescales. Its final response also failed to address concerns which the resident raised in her escalation request.

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

10 March 2026

2

Compensation order

The landlord must pay the resident £750, made up as follows:

  • £600 for distress caused by its failure to complete the works committed to in its final response within a reasonable timeframe.
  • £150 for distress caused by its complaint handling delays and failure to address issues the resident raised in her stage 2 escalation.

This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date.

No later than

10 March 2026

3

Communication order

The landlord must:

  • Maintain a single point of contact for the resident until it has completed any identified works.
  • Confirm how often it will update her on the progress of works.
  • Maintain a single point of contact for the resident until it has completed any identified works.
  • Confirm how often it will update her on the progress of works.

No later than

10 March 2026

3

Inspection order 

The landlord must contact the resident to arrange an inspection. It must take all reasonable steps to ensure the inspection is completed by the due date. The inspection must be completed by a suitably qualified person. If the landlord cannot gain access to complete the inspection, it must provide us with documentary evidence of its attempts to inspect the property no later than the due date.  

What the inspection must achieve 

 

The landlord must ensure that the surveyor: 

  • Inspects the downstairs rooms for any damp and mould. The surveyor must also produce a written report with photographs. 

The survey report must set out: 

  • Whether there is damp and mould within the property.
  • Whether the landlord is responsible to repair or resolve the issue(s) together with reasons where it is not responsible.
  • A full scope of works to achieve a lasting and effective resolution to the issue(s) (if the landlord is responsible). 
  • Whether this scope of works includes insulating the downstairs rooms.

The likely timescales to commence and complete the work. 

No later than

10 March 2026

Our investigation

The complaint procedure

Date

What happened

9 November 2023

The resident complained that there had been significant damp and

mould throughout the property since she moved in 8 years ago.

Specifically, she complained that:

  • The landlord had failed to address a patch of damp she reported on an internal wall during its recent inspection.
  • Her daughter’s bedroom was full of mould.
  • The skirting in the bathroom was rotting due to condensation from the toilet.
  • She was still waiting for the landlord to attend and address a roof leak.

5 February 2024

The landlord issued a stage 1 response. It explained that:

  • It completed a number of works to try and address the damp and mould from 2020 onwards.
  • It had raised works to insulate the flat roof up to the ceiling of the bathroom, and to insulate internal or external walls. It had added these works to its major works programme for 2022/23.
  • It acknowledged that there had been delays in progressing the works to insulate the property, and that it had thus far been unable to resolve the issues with the roof.

To address the damp and mould in the property, the landlord committed

to complete the following works within the next 6 months:

  • Remove coving and skirtings and set aside.
  • Remove dry lining to walls and dispose.
  • Use thixotropic cream sealer to the external surfaces.
  • Use 25mm insulated plasterboard dot and dabbed to external walls including window reveal.
  • Make sure carpet is protected.
  • Provide temp heaters if rads need removal.
  • Skim affected walls, when dry 1 coat watered down paint and 2 coats of white emulsion.
  • Refix skirtings and coving.
  • Internally insulate the resident’s daughter’s bedroom, 2x external walls only and affected windows.

It also offered the resident £1935 compensation, made up of:

  • £150 for the delay in our complaint being handled.
  • £70 for the administration errors in getting these issues rectified.
  • £400 for distress and inconvenience.
  • £1315 as an additional payment for distress and inconvenience as the issues was reported 22 December 2020 and we anticipate these issues will further need to be addressed in the next six months.”

9 February 2024

The resident escalated her complaint to stage 2. She complained the landlord’s stage 1 response had:

  • Underestimated the number of inspections completed in relation to damp and mould.
  • Failed to provide timescales for the insulation works, which she considered the main cause of the issue.
  • Failed to commit to insulate the entire property, as opposed to just her daughter’s bedroom.

25 April 2024

  • The landlord issued its stage 2 response. It explained that it had inspected the property and assessed the outstanding works committed to at stage 1. It had raised these works as a major repair and would be in touch to organise a start date.
  • It acknowledged the resident had been waiting for works to resolve the issues for some time and apologised for further delays. It also offered her another £200 compensation to put right any inconvenience this caused her.

Referral to the Ombudsman 17 January 2025

The resident complained she had been reporting widespread damp and mould for several years. She complained that, despite this, the landlord had not insulated every external wall of the property as per commitments it made to do so. She explained she wanted compensation and for the landlord to complete outstanding works.

8 January 2026

  • In a phone call with the resident, she advised us that she considered the landlord had fully resolved its omissions from 2020 until its stage 2 response in 2024. She explained she wants us to investigate the landlord’s failure to complete the insulation works it committed to at stage 2.
  • To resolve her complaint, she would like compensation for delays from April 2024 onwards, and for the landlord to insulate the external walls of the living room and kitchen.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

How the landlord handled works to address damp and mould.

Finding

Maladministration

  1. The resident considers the landlord has fully acknowledged and put right its omissions from 2020 until its 25 April 2024 stage 2 response. Her outstanding complaint is that it failed to suitably progress the works it committed to in its final response.
  2. We note the landlord paid the resident £2,135 compensation as redress for its pre-25 April 2024 omissions. This sum is higher than the upper end of the scale set out in our own guidance. With this in mind, we accept that it has already put right its omissions pre-25 April 2024. Therefore, this investigation will focus on how the landlord handled the works committed to on 25 April 2024.
  3. The landlord’s repairs policy explains that it will complete major works within 90 calendar days. It also states that it will keep residents updated about the progress of works.
  4. In its final response it committed to completing the following works:
    1. “Remove coving and skirtings and set aside.
    2. Remove dry lining to walls and dispose of.
    3. Use thixotropic cream sealer to the external surfaces.
    4. Use 25mm insulated plasterboard dot and dabbed to external walls including window reveal.
    5. Skim affected walls, when dry 1 coat watered down paint and 2 coats of white emulsion.
    6. Refix skirtings and coving.”
  5. It also explained that it had raised these works as a major repair. On 20 and 24 May 2025 we can see the landlord reskimmed walls in the bathroom and hallway. We can also see it replastered and applied new sealant throughout the bathroom. These works were therefore completed within its 90-day major repair timescale.
  6. There are then no repair records for works related to skirtings and covings, or the removal of dry lining to the walls. We recognise that landlords often have to adapt action plans in response to changing diagnoses of damp and mould issues. However, there is no audit trail to explain if these works were completed, and if they were not, why they were no longer necessary. We expect landlords to keep clear audit trails of works completed, and of any decisions they make to cancel outstanding works. There is no evidence of either here. On this basis, we are not persuaded the landlord handled these works appropriately.
  7. There is also no indication the landlord kept the resident informed about the progress of these specific works as per its repairs policy. We consider this likely caused the resident some distress.
  8. We can see the landlord insulated the internal wall between the bathroom and kitchen on 30 September 2025. However, as of 1 October 2025 it had yet to complete any works to insulate external walls as it committed to in its final response. The resident has advised that the landlord then insulated both upstairs bedrooms in late 2025, and that this resolved the damp and mould in these rooms.
  9. It therefore exceeded its major repairs timescales by at least 450 days here, and there is no evidence within the records to justify this delay. Furthermore, there is no evidence of any internal communication related to these works following its final response until 25 July 2025. This lack of action was unacceptable. We consider it likely caused the resident distress and delayed any resolution of the issues. There is also no evidence that the landlord kept the resident updated during this period. This likely compounded her distress.
  10. Therefore, the landlord failed to complete all of the works it committed to at stage 2 within its major repairs timescales. It also failed to keep the resident meaningfully informed about its actions. With this in mind, we have ordered the landlord to pay further compensation to put this right.
  11. Our compensation guidance sets out that payments of £100 to £600 are typically sufficient to put right failures which have adversely, but not permanently, impacted residents. The delay in completing the insulation works was significant and likely caused the resident significant distress. We also note that this distress was likely exacerbated given her evident concern about the impact of damp and mould on her children’s health. With these variables in mind, we will order the landlord pays a sum at the top end of our scale to put this right.
  12. While we have considered the distress this may have caused the resident, this investigation has not considered any potential impact of damp and mould on the resident or her children’s health. The courts are the most effective place for disputes about personal injury and illness. This is largely because independent medical experts are appointed to give evidence. They have a duty to the court to provide unbiased insights on the diagnosis, prognosis, and cause of any illness or injury. When disputes arise over the cause of an injury, oral testimony can be examined in court. Therefore, this part to the resident’s complaint is better dealt with via the court.
  13. The resident also complained that the landlord has failed to insulate external walls in the downstairs rooms. She explained that damp and mould continue to impact both the living room and kitchen as a result. We note that the landlord committed to insulate 1 bedroom only in its stage 1 response. However, in its final response it committed to insulate “external walls” and did not restrict this to any specific rooms. Therefore, given the ambiguity here, we will order the landlord to inspect the living room and kitchen and set out an action plan to address any issues identified. This will include setting out a position on whether it intends to insulate them.

Complaint

The handling of the complaint

Finding

Maladministration

  1. The landlord’s complaint handling policy sets out that it will acknowledge stage 1 complaints within 5 working days and respond within 10 working days of this. It will acknowledge stage 2 complaints within 5 working days and issue a response within 20 working days of this. When it is unable to do so, it will write to residents to explain this and provide updated timescales. This aligns with our Complaint Handling Code.
  2. The landlord acknowledged the resident’s stage 1 complaint within 5 working days. However, it was 34 working days late in issuing a response. It acknowledged the resident’s stage 2 escalation 7 working days beyond its timescale. It then issued its stage 2 response 41 working days beyond its timescale.
  3. We also note that, in her stage 2 escalation, the resident asked the landlord to clarify whether it intended to insulate every room in the property. Despite this, it did not offer any kind of meaningful clarification on this in its final response. Instead, it committed to insulate “external walls”. This was ambiguous and represented a missed opportunity to clearly set out its intended action plan. It was also not in keeping with our Complaint Handling Code, which sets out that landlords should respond to all issues raised in a complaint.
  4. The landlord has already paid the resident £150 compensation for the stage 1 delay. While we note this delay likely impacted her to some degree, we do not consider this impact went beyond minor frustration. Therefore, based on our own remedies guidance, we consider the landlord has already put this omission at stage 1 right with a proportionately minor sum.
  5. However, the landlord has not acknowledged the stage 2 delays, or its failure to offer clarification on which rooms it intended to insulate. We consider these omissions likely caused the resident some further frustration. For these reasons we have found maladministration. To put this right, we will order the landlord pays a sum at the low-mid range of our scale.

Learning

  1. The landlord’s handling of the works was generally poor. While it did well to complete the reskimming and sealing works, it failed to suitably progress the insulation works for at least 17 months. We would encourage the landlord to reflect on how it might have resolved any damp and mould in the property sooner had it been more proactive.

Knowledge information management (record keeping)

  1. The record keeping was poor for some of the works. Specifically, the landlord failed to record whether it completed the lining, skirting, or coving works. We would encourage the landlord to reflect on the importance of keeping clear audit trials for repairs.

Communication

  1. The landlord’s communication was poor following its final response. There is very little evidence of any meaningful communication with the resident to update her about the progress of works. We encourage the landlord to reflect on this and how better communication might have mitigated the impact of ongoing delays.