Karibu Community Homes Limited (202426405)

Back to Top

 

Decision

Case ID

202426405

Decision type

Investigation

Landlord

Karibu Community Homes Limited

Landlord type

Housing Association

Occupancy

Assured Tenancy

Date

17 February 2026

Background

  1. The property is a 3 bed house. The resident lives with his elderly parents. In September 2023 a leak started in his parent’s bedroom from a pipe in the loft. The landlord repaired the leak and agreed remedial works to the damaged ceiling. The resident complained in February 2024 because the landlord had not completed the repairs and decorations following the leak.

What the complaint is about

  1. The complaint is about the landlord’s handling of:
    1. Repairs following a leak and the associated offer of compensation.
    2. The associated complaint.

Our decision (determination)

  1. We found maladministration by the landlord in its handling of:
    1. Repairs following a leak and the associated offer of compensation.
    2. The associated complaint.

We have made orders for the landlord to put things right.

Summary of reasons

  1. The landlord accepted that its poor communication and management of contractors caused an unreasonable delay in completing the repairs. However, it did not fully address the detriment caused to the resident, or each of his complaint points in its responses. Its offer of compensation did not reflect the significant impact on the household in line with our Guidance on Remedies.
  2. The landlord did not acknowledge a complaint made by the resident. Its complaint responses at stage 1 and 2 were issued outside of the timescales set out in its policy and procedures. Its offer of compensation did not put things right in the circumstances.

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is provided by a senior manager.
  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

17 March 2026

2

Compensation order

The landlord must pay the resident £900 compensation. This is comprised of:

  • £700 for the distress and inconvenience caused by its handling of repairs following a leak and the associated offer of compensation.
  • £200 for the time and trouble caused by its handling of the associated complaint.

This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date.

The landlord may deduct from the total figure any payments it has already paid.

No later than

17 March 2026

 

Our investigation

The complaint procedure

Date

What happened

September 2023

On 18 September 2023, the resident reported a leak through a bedroom ceiling. The landlord attended on 21 September 2023 to inspect the roof. It determined that a broken pipe in the loft caused the leak, not the roof.

November 2023 – January 2024

The leak damaged the ceiling and walls in the bedroom and on the landing.

The landlord’s contractor removed damaged walls and the bedroom ceiling.

18 February 2024

The resident complained about the time taken to complete repairs following the leak.

14 June 2024

The landlord and resident exchanged emails. The resident said the landlord had replaced the ceilings in June 2024 but decorations were still outstanding.

21 June 2024

The resident complained to the landlord as follows:

  • He was unhappy that repairs were still outstanding from September 2023.
  • The landlord and contractor had given several dates to start the work that they had not fulfilled.
  • The repair delays meant his parents were unable to sleep in their bedroom and were sleeping in the living room.

 

The landlord acknowledged his complaint the same day and:

  • Agreed to urgently investigate the repair and ask its contractor to bring forward the start date for some works.
  • Apologised for the repairs delay and offered £300 compensation.

23 June 2024

The resident refused the landlord’s offer of compensation. He said that it did not reflect the time the repairs were ongoing.

16 July 2024

The landlord issued its stage 1 response:

  • It apologised for the delay and impact on the resident.
  • It said that it changed contractors in April 2024 which caused the delay.
  • It planned to complete the remaining repairs on 22 July 2024.
  • It offered the resident £400 compensation.

23 July 2024

The landlord’s notes show it spoke to the resident. He said he would be escalating his complaint to stage 2.

26 September 2024

The landlord issued its stage 2 response. It upheld his complaint. It said:

  • It was sorry for the way it handled the repairs. It apologised for poor communication and delays to complete repairs.
  • It acknowledged his time, trouble, distress and inconvenience.
  • It had changed contractors in April 2024 which caused problems with the previous contractor. It sent the repair to the new contractor as soon as it was able.
  • There were delays receiving quotes from the new contractor and in it authorising works. It had changed its approval procedure to ensure it completes repairs in a timely way.
  • It increased its offer of compensation to £450 compensation. This comprised of £400 for its handling of the repairs and £50 for its complaint handling.

Referral to the Ombudsman

The resident brought his complaint to us as:

  • He was unhappy with the amount of compensation offered.
  • He wanted more compensation for the distress and inconvenience caused by the delays.
  • He had decorated the walls himself after the landlord’s final response.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

Repairs following a leak and the associated offer of compensation

Finding

Maladministration

  1. The records show the damage to the resident’s bedroom, walls, and ceiling was considerable. The resident told the landlord that there was water leaking into a bedroom on 18 September 2023. He said he contained the water with buckets and asked it to inspect as an emergency. Before conducting any inspection, it arranged for a roofing contractor to inspect the roof. This caused a delay of 3 working days to identify the cause of the leak. Its initial response to the reported leak was unreasonable.
  2. The landlord has not disputed that there were delays completing the resulting repairs in its stage 2 response. It also accepted that that its communication with the resident between September 2023 and September 2024 was poor. It appropriately apologised for this and the issues caused by it changing contractor. While it was fair to apologise for the failings, the landlord did not fully address the delays identifying the cause of the leak early in the timeline.
  3. The resident said that the landlord agreed to decorate following the ceiling/wall repairs in 2023. In his emails to the landlord in June 2024, he said the landlord’s contractor had painted the ceilings but not returned to complete the wall decoration. In its stage 2 response in September 2024, the landlord appropriately acknowledged these concerns. However, it did not address them. It did not clarify what works were outstanding, or what it had previously agreed to. This was a failing which contributed to the resident’s distress and inconvenience.
  4. In his complaint to the landlord on 23 June 2024, the resident said he had taken additional time sending evidence to the landlord of the damage done by the leak. He said that it did not have proper records of the repair and the lack of communication between it and its contractor caused the delay. While the landlord acknowledged the communication failures and issues with its contractors, it did not use its complaint handling to effectively consider the impact on the resident’s time and trouble as a result.
  5. The landlord also failed to address the overall impact of the repairs on the resident and his family. He said that he was unable to use a bedroom for 9 months at the time of his complaint in June 2024. This meant his elderly parents slept in the living room during this period. This would have had a significant impact on him and his family. The landlord did not acknowledge this impact or show that it had put things right for the resident.
  6. We found maladministration by the landlord in its handling of repairs following a leak and the associated offer of compensation. We have considered the landlord’s compensation offer of £400 against our guidance on remedies. Our guidance says compensation of £600-£1,000 is reasonable for a failure which had a significant impact on the resident.
  7. In this case, the landlord acknowledged some of its failures but did not fully address them, or the impact on the resident across almost a year. Its recognition of some of its failures has been a mitigating factor when considering a reasonable remedy in this case. We have therefore ordered the landlord to pay an additional £300 compensation for the impact of its failures on the resident.

Complaint

The handling of the complaint

Finding

Maladministration

  1. The landlord’s complaint handling policy complies with our Complaint Handling Code. It will acknowledge complaints within 5 working days and issue responses at stage 1 within 10 working days and at stage 2 within 20 working days.
  2. The resident complained on 18 February 2024. The landlord did not acknowledge this complaint at the time or in its later responses and this was a failing. It caused the resident additional time and trouble as he complained again on 21 June 2024.
  3. The landlord acknowledged the second complaint 4 working days later, on 28 June 2024. It then issued its response 12 working days later, on 16 July 2024. It did not address or apologise for the delay in its stage 1 response.
  4. The records are unclear if the landlord treated the resident’s call on 23 July 2024 as a request to escalate his complaint. However, there is no other request to escalate recorded so we have considered that it did. Therefore, it is unreasonable that it took 47 working days to issue its stage 2 response, on 26 September 2024.
  5. The landlord appropriately acknowledged the delay in its stage 2 response. Its offer of £50 compensation was broadly reasonable for this delay. However, it failed to consider the resident’s earlier complaints or the delay at stage 1.
  6. We found maladministration by the landlord in its handling of the associated complaint. The landlord did not appropriately acknowledge the resident’s complaint in February 2024. It failed to issue its responses at both 1 and 2 within the timescales set out in its policy. Its offer of £50 compensation did not put things right in the circumstances.
  7. We have ordered the landlord to pay an additional £150 compensation for its complaint handling failures. This reflects our guidance on remedies for the landlords failure to fully address the resident’s additional time and trouble pursuing his complaint and the adverse impact as a result.

Learning

Knowledge information management (record keeping)

  1. The landlord acknowledged that there was a record keeping failure when it changed contractors in April 2024. It must ensure that it keeps clear and accurate records of repairs.

Communication

  1. The resident highlighted confusion in the landlord’s correspondence and lack of understanding of the outstanding repairs. This reflected its record keeping failures and in part resulted from its changing of contractors in April 2024.