Basildon Borough Council (202451868)
|
Decision |
|
|
Case ID |
202451868 |
|
Decision type |
Investigation |
|
Landlord |
Basildon Borough Council |
|
Landlord type |
Local Authority / ALMO or TMO |
|
Occupancy |
Secure Tenancy |
|
Date |
30 January 2026 |
Background
- The resident says her household includes 2 disabled children, one of whom has weak lungs and often has chest infections. She complained about the landlord’s handling of multiple repairs, and that a number of repairs identified in 2023 were outstanding.
What the complaint is about
- The complaint is about the landlord’s handling of:
- Repairs to electrics following a leak.
- Damp, mould, and ceiling repairs.
- Bathrooms repairs.
- Reports regarding the loft insulation and roof.
- A request for a full asbestos survey.
- The complaint.
Our decision (determination)
- There was no maladministration in the landlord’s handling of repairs to electrics following a leak.
- There was maladministration in the landlord’s handling of damp, mould, and ceiling repairs.
- There was maladministration in the landlord’s handling of bathrooms repairs.
- There was no maladministration in the landlord’s handling of reports regarding the loft insulation and roof.
- There was no maladministration in the landlord’s handling of a request for an asbestos survey.
- There was service failure in the landlord’s handling of the complaint.
We have made orders for the landlord to put things right.
Summary of reasons
Repairs to electrics following a leak
- The repairs were scheduled and completed in a reasonably timely manner.
Damp, mould and ceiling repairs
- Some of the identified repairs have not progressed in any substantial way since 2023.
Bathrooms repairs
- The works to remove asbestos flooring and renew flooring were not appropriately progressed.
Reports regarding the loft insulation and roof
- The landlord inspected and completed identified works to renew the loft insulation and roof in a timely manner after the complaint.
Requests for a full asbestos survey
- The landlord was not required to do a full asbestos survey of the nature the resident requested.
Complaint handling
- The landlord missed the opportunity presented by the complaints procedure to effectively monitor and resolve the issues.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:
|
No later than 27 February 2026 |
|
|
Compensation order The landlord must pay the resident £600 to recognise the distress and inconvenience caused her and the time and trouble she has gone to. This comprises £400 for the damp, mould and ceiling repairs, £100 for the bathrooms repairs, and £100 for the complaint handling. This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date. |
No later than 27 February 2026 |
|
|
Inspection order The landlord must contact the resident to arrange a joint inspection, by a senior repairs representative of the landlord, and senior representative of its contractor, to inspect outstanding works for:
It must take all reasonable steps to ensure the inspection is completed by the due date. If the landlord cannot gain access to complete the inspection, it must provide us with documentary evidence of its attempts to inspect the property no later than the due date. What the inspection must achieve The landlord must:
The report must set out its findings on the above and detail:
|
No later than 13 March 2026 |
Recommendations
Our recommendations are not binding, and a landlord may decide not to follow them.
|
Our recommendations |
|
The landlord is recommended to consider its obligations under the Equality Act 2010 and:
|
Our investigation
The complaint procedure
|
Date |
What happened |
|
23 January 2025 |
The resident verbally complained to the landlord.
|
|
27 January 2025 |
The landlord responded at stage 1:
|
|
28 January 2025 |
The resident escalated her complaint:
|
|
4 February 2025 |
The landlord responded at stage 2:
|
|
Referral to the Ombudsman |
The resident asked us to investigate. She raised dissatisfaction with delays, management and communication in respect to the repairs. She said multiple repairs remain outstanding, and is seeking for these to be completed. |
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
Repairs to electrics following a leak |
|
Finding |
No maladministration |
- The resident complained that she had to chase follow-on electric repairs for a leak. She also complained that the landlord then scheduled the repairs, including restoration of landing lighting, in a month’s time. She said this was too long since her children were partially sighted. The landlord’s stage 1 response said that the repairs were scheduled for 17 February 2025 and it would bring them forward if possible. Its stage 2 response then confirmed it had brought them forward to 30 January 2025.
- The evidence shows that the resident reported a leak on 11 January 2025 (a Saturday) and the same day, an operative fixed a loft pipework leak, made safe electrics, and reported a follow-on repair for lighting and a smoke alarm. The follow-on repair was then raised on 13 January 2025 (a Monday), the same day the resident chased, and scheduled for 17 February 2025. They were then rescheduled and completed on 30 January 2025 after the resident escalated the complaint on 28 January 2025.
- The landlord responded to the leak the same day and in a timely manner. The resident says she had to chase the follow-on repair, which may have been frustrating, but the follow-on repair was also raised in a timely manner as this was raised the Monday after the leak and within 1 working day. The landlord was then positive to bring the follow-on repair for the landing lighting and smoke alarm forward. These were scheduled and completed in a reasonably timely way.
- While the above is the case, the resident’s reports of her children being partially sighted could have prompted clearer consideration about whether reasonable adjustments could be made for the timeframe of the follow-on repairs. The landlord and its contractor discussed the possibility of bringing the repairs forward, and did eventually bring them forward. But it is not evident that the children’s partial sight, the nature of the repair and the risk were a clear consideration, as may be reasonably expected.
- It is not evident that any significant detriment was caused by the time it took to restore the landing lighting, and the landlord noted the resident was happy with the repair being brought forward. However, we recommend the landlord to ensure that it clearly considers reasonable adjustments in similar circumstances, in line with its complaints policy which says its aims include “respecting the diversity of service users and providing reasonable adjustments where necessary.”
|
Complaint |
Damp, mould, and ceiling repairs |
|
Finding |
Maladministration |
- The resident complained that the landlord had not raised repairs for ceilings and walls when she had raised these after the January 2025 leak. She said there had been a lack of action after operatives had previously attended for reports of black mould on the bathroom ceiling. She also said there was still something wrong with a kitchen extractor fan, after she had reported that she experienced condensation when she cooked and operatives had found the kitchen extractor to work.
- The landlord’s complaint responses acknowledged and apologised that there had been a lack of progress to some repairs, which included reinstatement of the bathroom ceiling, identified in late 2023. It confirmed it had scheduled a February 2025 inspection and mould treatment for the ceilings, a February 2025 repair for the kitchen extractor, and March 2025 works for the bathroom ceiling.
- The evidence shows that the resident’s most recent reports about damp and mould before her complaint were around October 2023, when the landlord raised a repair for damp and mould to bedroom and bathroom ceilings. In November 2023, a repair was then raised which included works to remove asbestos from 1 square metre of the bathroom ceiling and reinstate the ceiling. The ceiling works did not subsequently progress, although the landlord attended in early 2024 for other works.
- The resident then reported a loft pipework leak on 11 January 2025, which she reported affected every room upstairs. On 23 January 2025, the day the resident complained, the landlord raised a repair to inspect ceilings and walls, raised a repair to overhaul the kitchen extractor fan, and re-raised the repair to replace 1 square metre of the bathroom ceiling.
- The landlord was appropriate to acknowledge and apologise that the bathroom ceiling works identified in November 2023 were delayed, and to confirm that it had raised repairs for this and other issues the resident raised. This was potentially proportionate action for the damp and mould issues that the resident reported. However, multiple issues have not progressed in any substantial way.
- The landlord said in its response that any necessary mould treatment would be carried out at a February 2025 visit. Its repairs records show no evidence of a mould treatment being raised and the resident says this was not done.
- The landlord’s contractor attended in February 2025 to inspect multiple ceilings. They noted issues with water damage and identified works to remove and replace a part of a large bedroom ceiling, remove and replace the whole of a small bedroom ceiling, and repair a landing ceiling. Its repairs records show no evidence of these being raised. The resident says no ceiling works have been done and provided photos of water-stained bedroom ceilings.
- The landlord’s contractor attended in March 2025 to replace the bathroom ceiling, and its records note the repair was completed then, but the resident says this was not done. She says that when operatives attended to remove the ceiling asbestos, they agreed more works were needed than noted, and said they would report this back. She says that as she felt there was no point in doing only 1 square metre of the bathroom ceiling, the bathroom ceiling was patched with black duct tape. She says the ceiling has been left in this condition, despite chasing the contactor.
- The resident confirms that the landlord’s contractor attended to overhaul the kitchen extractor fan and said it needed to be cleaned. She says it does not work and is not in a suitable location.
- This shows that the bedroom and landing ceiling works were not progressed after a February 2025 inspection identified works. The kitchen fan was not overhauled in line with the raised repair and it is unclear that the issue has been addressed in an effective way. The bathroom ceiling has continued to not be repaired after the works were originally identified in November 2023. It not evident that a mould treatment was raised and done as committed to by the complaint responses.
- This is not satisfactory, particularly since part of the resident’s complaint was a lack of follow-up to works and communication between the contractor, the landlord and her. The issues and delays seen in 2023 have continued which suggests the landlord and contractor have not taken effective enough steps to try to avoid them.
- We do not make definitive decisions about causes for the impact on health, and it is not clear that issues have had a significant detriment. However, the landlord has not shown sufficient regard for the resident’s concerns that issues posed a health risk to her vulnerable children.
- The photos the resident provided also show water damaged ceilings and the bathroom ceiling with a large area of black material taped to it. The black material may have helped mitigate against mould, but these will be unsightly and unpleasant conditions to live in.
- The landlord’s continued lack of resolution of the issues will have caused distress, inconvenience and frustration to the resident. We order the landlord to pay £400 to recognise this and take some specific repairs actions, after considering the evidenced service issues, impact and our remedies guidance.
- We note the resident raised concerns that some historical appointments for damp and mould were recorded as no access. She said her husband is deaf and operatives should have telephoned when they attend for repairs to avoid these being missed.
- This does not seem to have been a specific issue in the complaint timeframe. The landlord’s response that she should raise this preference when speaking to the contractor about repairs was not unreasonable, as this was after the landlord discussed the issue with the contractor. However, recommendations are made about this.
|
Complaint |
Bathrooms repairs |
|
Finding |
Maladministration |
- The resident complained about some previous bathroom repairs and a lack of follow-up after operatives said asbestos checks were required. These are understood to have been to repair previous water damage. The landlord’s complaint responses acknowledged and apologised that there had been a lack of progress to some repairs, which included a cistern leak, renewing flooring in 2 bathrooms, and repairing boxing behind a toilet. It confirmed it had scheduled a February 2025 repair for the cistern leak, scheduled an April 2025 repair for the boxing, and said it would progress the flooring after this had been asbestos tested.
- The evidence shows that in November 2023, a repair was raised which included works to repair the cistern leak, renew flooring in 2 bathrooms, and repair boxing behind the toilet. The landlord’s contractors attended for the works in January and May 2024, but reported that asbestos tests and removal was required, and the works did not progress. The resident confirms the cistern leak was repaired but says it has been a recurrent issue.
- The landlord confirmed it re-raised the repairs after the resident’s January 2025 complaint, and it repaired a cistern leak in February 2025 and rotten boxing in April 2025. However, it is not evident that works to remove asbestos flooring and renew flooring have progressed, until the resident reported a further leak in November 2025. The landlord raised further flooring works after these in December 2025 and January 2026, but it is unclear these are complete, and there is evidence of further delays due to the asbestos team not attending to remove flooring.
- The landlord was appropriate to acknowledge and apologise that the bathroom works identified in November 2023 were delayed, and to confirm that it had re-raised repairs for them. This was potentially proportionate action for these issues. However, the flooring did not progress in any substantial way in the 9 months after the landlord’s complaint response and cistern leak repair, and in the 7 months after the boxing repair.
- This is not satisfactory, particularly since part of the resident’s complaint was a lack of follow-up to works and communication between the contractor, the landlord and her. The issues and delays seen in 2023 have continued which suggests the landlord and contractor have not taken sufficiently effective enough steps to try to avoid them.
- The evidence is not clear that the outstanding bathroom repairs have had a significant detriment, but the continued lack of resolution will have caused distress, inconvenience and frustration to the resident.
- We order the landlord to pay £100 to recognise this and take some specific repairs actions, after considering the evidenced service issues, impact and our remedies guidance.
|
Complaint |
Reports regarding the loft insulation and roof |
|
Finding |
No maladministration |
- The resident complained there had been a lack of follow up for a recommendation to renew loft insulation, and that a stock survey had found a new roof was required. The landlord’s complaint responses noted that in 2022 a contractor had recommended for the loft insulation to be renewed, and that in 2023 a surveyor had said the roof would require renewal in 2030. It confirmed it had scheduled a February 2025 inspection for the roof.
- The evidence shows that in 2021 some roof works were raised and completed, in 2022 loft insulation was recommended to be renewed after a leak (which did not progress), and the resident confirms a stock condition survey of the roof was done in 2023.
- The landlord confirmed it had raised an inspection after the resident’s January 2025 complaint, and the February 2025 inspection reported that insulation works were needed and the roof felt was in poor condition. Following this, the landlord erected scaffold in June 2025 and completed works to renew the roof, insulation, gutters, fascias and soffits around July 2025.
- The 2022 recommended insulation works did not progress, which is not entirely satisfactory, but it is unclear this resulted in significant detriment. It is unclear there was a significant failing for the roof, as this was previously identified to require renewal in 2030. They also relate to events over a year before the resident’s complaint.
- The landlord’s response to acknowledge the lack of progress for the loft insulation and arrange for an inspection of the loft and roof was overall proportionate in the circumstances. This gave it the opportunity to inspect the current condition of the loft insulation and roof and take any identified action. The landlord appropriately progressed and completed works it identified to renew the loft insulation and roof. The 5 months these took was reasonably timely, given the nature of the works.
|
Complaint |
A request for a full asbestos survey |
|
Finding |
No maladministration |
- The resident said in her complaint escalation that she sought a full asbestos survey of her home. She said this was because of the works required, her and contractors having inaccurate information, and her concerns it was a health risk. The landlord responded that it was unable to agree to the request, as a survey was done in 2014, and it only requested asbestos tests in areas it intended to do works.
- The resident has understandable concerns about handling of works and delays where there have been requests for asbestos checks, which other findings reflect. However, the landlord’s response to the request for a full asbestos survey was reasonable and reflects evidence seen.
- The landlord carried out an asbestos survey in 2014 which identified some areas where asbestos was confirmed or presumed. Its repairs policy says that if tenants suspect damaged asbestos or intend to do works that may disturb asbestos, they should call a number or refer to its website. Its contractors are entitled to have a similar approach in requesting asbestos checks when asked to do works in areas they suspect there may be asbestos. It is not evident that the landlord is obligated to do a full asbestos survey of the nature the resident requested.
|
Complaint |
The handling of the complaint |
|
|
Finding |
Service failure |
|
- The landlord has a 2-stage complaint process. It aims to acknowledge complaints within 5 working days. It then aims to provide a formal response within 10 working days at stage 1, and within 20 working days at stage 2. The landlord provided acknowledgements and responses in these timescales and in line with our Complaint Handling Code.
- However, the landlord is reasonably obligated to ensure it meets commitments it makes. Our Complaint Handling Code says that where complaint responses detail outstanding actions, as in this case, these “must still be tracked and actioned promptly with appropriate updates provided to the resident.”
- The landlord has not acted in line with this. It has missed the opportunity presented by the complaints procedure to effectively monitor and resolve the substantive issues. The continued lack of resolution, despite making a complaint, will have caused further frustration to the resident and undermined her confidence. We order the landlord to pay £100 to recognise this, after considering the evidenced service issues, impact and our remedies guidance.
Learning
- As noted above, multiple repairs have remained uncompleted, despite the resident making a complaint and the landlord making commitments to complete them. The landlord could reflect on this and any service improvements it could make, to try to ensure that repairs which are the subject of complaints are effectively monitored and completed
Knowledge information management (record keeping) and communication
- The evidence shows multiple instances where operatives have attended and identified works that have not progressed, including when they have identified that an asbestos check is required, without clear reasons why. This indicates issues with the landlord’s record keeping, internal communication, and handling of works where follow up is required.
- The landlord could reflect on these and particularly review whether it has sufficient processes in place to respond to contractor requests for asbestos checks, and to monitor and progress the related works, to ensure these are completed in a timely manner.