Orbit Housing Association Limited (202431910)

Back to Top

Decision

Case ID

202431910

Decision type

Investigation

Landlord

Orbit Housing Association Limited

Landlord type

Housing Association

Occupancy

Secure Tenancy

Date

4 December 2025

Background

  1. The resident reported a leak into his flat from the roof. The landlord took some steps to carry out repairs. However, the resident complained to the landlord that the issue was unresolved. Through a settlement agreement the landlord agreed to pay the resident compensation and complete the roof works and associated repairs. The resident remains unhappy with how the landlord responded to his reports and has concerns that the leak remains unresolved.

What the complaint is about

  1. The complaint is about the landlord’s handling of the resident’s reports of a roof leak.
  2. We have also assessed the landlord’s complaint handling.

Our decision (determination)

  1. We have found that there was:
    1. Service failure in the landlord’s handling of the resident’s reports of a roof leak.
    2. Reasonable redress in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

  1. The landlord missed several opportunities to progress and resolve the resident’s reports of the leak. There is also no evidence that it had learnt lessons from its failings.
  2. The landlord offered proportionate compensation for its delayed complaint responses.

 

Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

13 January 2026

2

Inspection Order

We have made an inspection order because it is unclear whether the leak has been fully resolved.

The landlord must:

  • contact the resident to arrange an inspection.
  • take all reasonable steps to ensure the inspection is completed by the due date. A suitably qualified person must complete the inspection. If the landlord cannot gain access to complete the inspection, it must provide us with documentary evidence of its attempts to inspect the property no later than the due date.
  • provide the resident and us with a written outcome of the inspection.

If further roof works are required, they should be completed, alongside any associated repairs within a reasonable timeframe and the landlord should consider whether additional compensation is warranted.

No later than

3 February 2026

3

Review Order

The landlord should carry out a review, taking into consideration the failings outlined in this report. In particular it should ensure its repairs, record keeping and communication practices are robust and staff are adequately trained to proactively monitor and progress repairs until completion.

 

No later than

10 March 2026.

4

Action Order

Pay the resident the compensation it offered in its complaint responses if it has not done so already.

No later than

13 January 2026

 

 

Our investigation

The complaint procedure

Date

What happened

January – September 2023

The resident reported that there was a roof leak in January 2023. In September 2023 the landlord completed roof works.

31 October 2023

The resident told the landlord that the roof leak was not resolved.

19 June 2024

The resident made a complaint. He said:

  • the 2023 roof works were not completed and there was an ongoing leak. There were also cracks in the ceiling.
  • the landlord last attended in November 2023 but no further action was taken.

5 September 2024

The landlord issued its stage 1 complaint response. It said it would carry out another investigation into the leaks by 3 October 2024.

It offered the resident £350 compensation for time, trouble and inconvenience and £100 for its delayed complaint response.

30 September 2024

The resident escalated his complaint as the landlord failed to attend as advised.

13 November 2024

The landlord issued its stage 2 response. It said:

  • It did not detect any roof leaks in its August 2024 inspection.
  • It would carry out remedial works to the roof by 2 December 2024. Then it would inspect the repairs to see whether the matter was resolved.
  • The ceiling cracks were a result of the leaks, and it would repair these once the leaks were resolved.
  • It wished to offer a further £100 compensation for the delays in resolving the roof leak and £50 for the delayed stage 2 complaint response.

November 2024 onwards

  • In February 2025, the resident asked his solicitor to work with the landlord so the leak could be resolved.
  • Around August 2025 a settlement agreement was made between the resident and landlord. The landlord paid the resident £2700 compensation and said that it would complete the roof works and associated repairs by 15 October 2025 as part of the agreement.

Referral to the Ombudsman

The resident told us that the landlord has not resolved the roof leak which has caused him distress and inconvenience.

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of the resident’s reports of a roof leak

Finding

Service failure

  1. It is clear that the landlord missed several opportunities to appropriately resolve the resident’s concerns that there was a roof leak.
  2. The landlord should have taken reasonable steps to investigate the issue when the resident told it that the leak was not resolved in October 2023. However, the evidence available shows that it noted that the repairs were completed in September 2023 without further investigation. The reason that the landlord did not carry out any meaningful investigations into the resident’s concerns at this time is unclear. Nonetheless, that it did not was a missed opportunity to ensure that no further works were required to fully resolve the issue. If it had done so, it may have mitigated further distress and inconvenience incurred by the resident.
  3. When the resident complained that the leak had not been resolved in June 2024, the available evidence shows that the landlord did not raise an order to investigate the repair until August 2024. While the reason for the delay is unknown, that there was one is a further failing that exacerbated the resident’s distress and inconvenience as his concerns went unaddressed.
  4. In its stage 2 response, the landlord stated that it had not identified any leaks when it attended in August 2024. While the landlord’s comments are noted, we have not been provided with any contemporaneous evidence in relation to this. As such, the landlord has failed to demonstrate how it reached its conclusion and that it was correct.
  5. The landlord went on to advise in its stage 2 response that remedial works would be undertaken. How and when the landlord identified these repairs is unclear. Especially given its comments regarding the August 2024 inspection and that no leaks were identified at that time. Nonetheless, in its stage 2 response the landlord told the resident that it would carry out the works to the roof by 2 December 2024. It also said that it would carry out a post inspection once the works were completed.
  6. We do not have contemporaneous records of the outcome of these orders and actions either. Therefore the landlord has failed to demonstrate that it reasonably followed through with these commitments. Whether the landlord does not have the information mentioned above, if no record was kept, or if it failed to provide it for the purposes of this investigation is unclear. Regardless, this is a record keeping issue.
  7. There is also no evidence that it meaningfully updated the resident about the outcome of its actions during this period either. That is unreasonable and would have added to his distress.
  8. In February 2025 the resident contacted his solicitor in a bid to progress the repairs with the landlord as the leak went unresolved. Given that the resident had already raised his concerns as a formal complaint, it should not have been necessary for him to seek the assistance of a solicitor. This caused him time, distress and inconvenience that may have been avoided if the landlord had taken meaningful and appropriate steps to resolve the leak.
  9. Given the several failings identified before and after its stage 2 response, we are not satisfied that the landlord learned from this situation. Therefore, we have found that there was a service failure in its handling of the resident’s reports of a leak. We have made an order for the landlord to carry out a case review to ensure similar failings do not occur in the future.
  10. In August 2025 both parties approved a settlement agreement in relation to the leak and associated repairs. The landlord paid the resident £2700 and agreed to carry out repairs by 15 October 2025 as part of the agreement.
  11. We have concluded the offer was reasonable because the resident accepted it based on advice from his legal advisors and that it was the type of award we could have made for its handling of the matter from 2023 onwards. It is noted that the landlord also offered compensation in relation to its failings within its complaint responses before additional compensation was paid through the agreement. Taking the above into consideration, no further compensation has been awarded.
  12. The landlord has told us that works have been carried out, no further leaks have been reported and it has arranged to carry out internal repairs. However, the resident has told us that the leak has not been resolved. He explained that the landlord attended at the end of November 2025 to complete internal repairs but was unable to carry out the work because the leak was still present. He told us that a 2025 property report stated that the roof should be replaced, but the landlord has not done so.
  13. It is unclear whether the landlord has carried out a recent post inspection of the roof repairs. Given the resident’s concerns an order has been made for it to complete one. It should provide the resident and us with a written outcome of the inspection. The landlord should consider offering the resident further compensation if further roof works are required.  If they are, they should be completed, alongside any associated repairs within a reasonable timeframe. The resident may wish to consult with his solicitors if he wishes to legally pursue the matter further as outlined in the settlement agreement.

Complaint

The handling of the complaint

Finding

Reasonable redress

  1. The landlord’s complaint policy stated that it would respond to stage 1 and 2 complaints within 10 and 30 working days respectively. However, it issued its stage 1 within 50 working days and its stage 2 response within 32 working days. The landlord acknowledged its failings and offered the resident £150 compensation for its delayed response. Given the length of time of the delays this was reasonable and in line with our Remedies Guidance. Therefore we have found that there was reasonable redress in the landlord’s complaint handling.
  2. It is noted that at the time of the complaint, the landlord’s stage 2 response timescale was not in accordance with our Complaint Handling Code (the Code). However, the landlord has since revised its response times to align with the Code.

Learning

Knowledge information management (record keeping) and Communication

  1. The evidence suggests that the landlord’s poor record keeping and communication practices contributed to its failings in this case. An order for the landlord to carry out a case review has been made.