Clarion Housing Association Limited (202338846)
|
Decision |
|
|
Case ID |
202338846 |
|
Decision type |
Investigation |
|
Landlord |
Clarion Housing Association Limited |
|
Landlord type |
Housing Association |
|
Occupancy |
Assured Tenancy |
|
Date |
17 December 2025 |
Background
- The resident lives in a flat with his young family on the third floor. He reported the communal lift was not working numerous times and raised a complaint about how long it took to repair it.
What the complaint is about
- The complaint is about the landlord’s handling of repairs to the communal lift.
- We have also investigated the landlord’s handling of the complaint.
Our decision (determination)
- We have found there was:
- Service failure in the landlord’s handling of repairs to the communal lift.
- Service failure in the landlord’s handling of the complaint.
We have made orders for the landlord to put things right.
Summary of reasons
The landlord’s handling of repairs to the communal lift
- The landlord delayed repairing the lift as it failed toidentify that a part was needed at the earlier opportunity.
- The landlord appropriately acknowledged that the resident and his family were inconvenienced as a result of the lift being out of order. However, the level of compensation offered by the landlord did not reflect the detriment caused.
The landlord’s handling of the complaint
- The landlord took some steps to engage with the complaint in a meaningful way. However, it missed an opportunity to put things right and did not appropriately reflect on its handling of the repair to identify any learning from it.
Putting things right
Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.
Orders
Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.
|
Order |
What the landlord must do |
Due date |
|
1 |
Apology order The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:
|
No later than 14 January 2026 |
|
2 |
Compensation order The landlord must pay the resident £250 compensation made up as follows:
It must also pay the resident the £150 it offered in its stage 1 complaint response if it has not done so already. This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date. |
No later than 14 January 2026 |
|
3 |
Review order The landlord should carry out a review of how it handled the lift repair. It should particularly focus on the delay caused by not identifying the part that was needed sooner. It should consider how it could have done things differently and what it can do to prevent this happening again. The landlord should provide us with a copy of its review by the due date. |
No later than 14 January 2026 |
Our investigation
The complaint procedure
|
Date |
What happened |
|
November 2023 |
The resident reported the lift was not working on 26 and 28 November 2023. The landlord attended on each occasion within 1 working day and left the lift in service. |
|
December 2023 |
The resident reported the lift was not working 11 times between 2 and 28 December 2023. The landlord attended on each occasion within 1 working day and left the lift in service. During 6 of these attendances (between 13 and 28 December 2023) it identified that the same part was causing the lift to breakdown. |
|
13 December 2023 |
The resident raised a complaint to the landlord about the reoccurring breakdown of the lift. |
|
20 and 27 December 2023 |
The resident chased the landlord for an update about the lift repair. |
|
29 December 2023 |
The landlord told the resident the relevant part had been ordered but it did not have an estimated delivery date. The resident replied and expressed concern that a contractor had told him 3 weeks prior that the part was needed, and that it was waiting for it to be ordered. |
|
January 2024 |
The resident reported the lift was not working on 4, 11 and 17 January 2024. |
|
2 January 2024 |
The landlord sent a letter to all residents to tell them the part needed for the lift had been ordered but had a 10-day delivery time frame. |
|
19 January 2024 |
The landlord attended to replace the relevant part and left the lift in service. |
|
31 January 2024 |
The landlord issued its stage 1 response. It said:
|
|
31 January 2024 |
The resident escalated his complaint to stage 2 as he was unhappy with the amount of compensation offered. He said his family’s daily living activities had been severely limited as a result of the lift being out of service, in that:
|
|
26 February 2024 |
The landlord issued it stage 2 response. It reiterated what it said in its stage 1 response and confirmed that it considered the level of compensation offered was appropriate. |
|
Referral to the Ombudsman |
The resident contacted us on 28 February 2024 as he was unhappy with the landlord’s response to his complaint. He was not satisfied with the amount of compensation that had been offered. |
What we found and why
The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.
|
Complaint |
The landlord’s handling of repairs to the communal lift |
|
Finding |
Service failure |
- The landlord’s lift maintenance policy says it will repair and maintain lifts to the approved standard within agreed timescales and will deal with any emergency quickly. It will also keep residents informed about issues with lifts that may affect them directly and help residents that are adversely affected by the loss of a lift service.
- The resident reported the lift was not working 13 times in November and December 2023. On each occasion the landlord appropriately attended, made repairs and left the lift in service. This was appropriate.
- However, given the frequency of breakdowns, it is unclear why the landlord did not adopt a more holistic approach to the problem. Had it done so, it may have identified whether there was a recurring fault, and carried out a more lasting repair. While the landlord said it requested a full report on the ongoing faults with the lift there is no evidence provided to show it did this. The evidence therefore does not demonstrate that the landlord explored this fully. We consider this was a shortcoming in the landlord’s overall approach.
- The resident was told by the landlord a part was needed on 29 December 2023. He replied and said the contractor had told him 3 weeks previously this part was needed and was waiting on the landlord to authorise the order for it. We have not seen that the landlord responded to this comment from the resident. As such it could reasonably have been more transparent with the resident about the lift issues,
- The part was subsequently ordered on 2 January 2024. It is unclear why this was not ordered sooner. The landlord’s comments that the supplier was closed for Christmas are acknowledged. However, it is also noted that the part in question had been identified as the reason for the breakdown earlier in December 2023, before the Christmas holiday. In the absence of any other evidence, the landlord delayed unreasonably in ordering the part and progressing the repair.
- The resident reported the lift was not working a further 4 times from 29 December 2023 to 19 January 2024. It is unclear why the landlord did not attend. While we acknowledge the relevant part was on order, it would have been reasonable to attend and respond to the report that had been raised. The evidence does not show that it did so.
- When the landlord responded to the complaint, it appropriately acknowledged that he and his family had been inconvenienced. While it was reasonable for it to offer the resident some compensation, we are not satisfied that its offer of £100 was proportionate.
- The resident reported numerous times the lift had broken down and chased the landlord for updates over a 2-month period. He also advised of the impact caused to his household by the breakdowns as he lived on the third floor. Given the resident’s testimony, and the offer which was made, the landlord failed to fully consider the detriment caused as a result of its handling of matters and therefore did not put things right for him.
- As such we have directed the landlord pay him further compensation for the time and trouble suffered by him in reporting the issues with the lift and the difficulty caused to his day to day living. The landlord’s compensation policy for service failure has a range of £50 to £250. It is unclear why it did not consider a more proportionate offer within this range to reflect the cumulative impact caused by the period the lift was out of service, the frequency of breakdowns outside of that time, and the inconvenience in having to chase updates.
|
Complaint |
The landlord’s handling of the complaint |
|
Finding |
Service failure |
- The Complaint Handling Code (‘the Code’) published in 2022 applied when the resident made his complaint. The landlord used an interim complaint policy at the time due to a cyber-attack. The policy said the landlord would respond at stage 1 within 20 working days and within 40 working days at stage 2.
- The landlord issued its stage 1 response 26 working days after the complaint acknowledgement. The landlord appropriately apologised for this delay in its complaint response and offered £50 compensation. In line with our Remedies Guidance, we are satisfied that this compensation was proportionate given the length of delay at this stage. We therefore find the landlord provided reasonable redress to its failure to respond to the complaint within appropriate timeframes. The landlord responded within its policy time frame for stage 2.
- However, the resident had raised dissatisfaction with the compensation that was offered at stage 1. When the landlord responded at stage 2, it simply confirmed the amount of compensation was appropriate. While it may have considered this to be the case, it missed an opportunity to explain its decision further, and to help the understand why it felt it had taken appropriate and proportionate steps to put things right. As a result, the resident’s concerns about the level of compensation went unaddressed.
- In addition, the landlord also missed an opportunity to fully review its handling of the lift repair and to set out any learning that had been identified as a result of the complaint. As such, the landlord’s complaint handling could reasonably have been improved, and we have found that there was service failure.
Learning
- The landlord caused delays to the lift repair by not ordering the part sooner. We have made a relevant order related to this.
Knowledge information management (record keeping)
- The landlord’s recording keeping was appropriate and allowed us to fully investigate the issues raised.
Communication
- The landlord appropriately communicated directly with the resident responding to his reports about the lift and providing updates to him when it could.