West Northamptonshire Council (202323688)

Back to Top

Decision

Case ID

202323688

Decision type

Investigation

Landlord

West Northamptonshire Council

Landlord type

Local Authority / ALMO or TMO

Occupancy

Secure Tenancy

Date

27 November 2025

Background

  1. The resident lives in a 3 bedroom house with her 3 children. She complained that the landlord failed to complete roof repairs which had caused the ceiling to collapse in her child’s bedroom.

What the complaint is about

  1. The complaint is about the landlord’s handling of:
    1. Roof repairs.
    2. The complaint.

Our decision (determination)

  1. We have found:
    1. There was service failure in the landlord’s handling of roof repairs.
    2. There was maladministration in the landlord’s complaint handling.

We have made orders for the landlord to put things right.

Summary of reasons

  1. There were delays in repairing the roof and the landlord acknowledged them in its complaint response. It explained how the delays had occurred, apologised and awarded compensation.  However, it did not fully consider the impact on the resident in its offer of compensation and did not fully put things right.
  2. The landlord failed to escalate the resident’s complaint to stage 2. It did not provide a response until this Service intervened.


Putting things right

Where we find service failure, maladministration or severe maladministration we can make orders for the landlord to put things right. We have the discretion to make recommendations in all other cases within our jurisdiction.

Orders

Landlords must comply with our orders in the manner and timescales we specify. The landlord must provide documentary evidence of compliance with our orders by the due date set.

Order

What the landlord must do

Due date

1

Apology order

The landlord must apologise in writing to the resident for the failures identified in this report. The landlord must ensure:

  • The apology is specific to the failures identified in this decision, meaningful and empathetic.
  • It has due regard to our apologies guidance.

No later than

06 January 2026

2

Compensation order

The landlord must pay the resident £1250 made up as follows:

£900 awarded following the stage 2 response.

£200 for failures in its handling of roof repairs.

£150 for complaint handling failures.

 

This must be paid directly to the resident by the due date. The landlord must provide documentary evidence of payment by the due date.

The landlord may deduct from the total figure any payments it has already paid.

No later than

06 January 2026

3

The landlord should review the evidence it has from November 2022 to November 2023 and decide if the bedroom effected by the leak was unusable during that period. It should then consider if compensation is appropriate and set out its decision on this to both the resident and this Service.

No later than

06 January 2026

 


Our investigation

The complaint procedure

Date

What happened

28 September 2023

The resident raised a complaint. She had waited since November 2022 for the landlord to fix the roof and was unhappy with the service received. She wanted to know when the repairs would be completed.

23 October 2023

The landlord responded at stage 1. It upheld the complaint and agreed that the delay was unacceptable. It said it had asked its roofing contractor to prioritise this work and apologised for the delays.

5 November 2023

The resident was not satisfied with the landlord’s response and asked to escalate her complaint to stage 2. She said her children had been put at risk because the ceiling collapsed after temporary repairs. She explained she had been told the ceiling was safe before the collapse occurred. She requested financial compensation for the inconvenience and to cover the cost of damaged items.

1 February 2024

The landlord responded at stage 2, it upheld the complaint and said:

  • Roof repairs were completed on 20 November 2023; the delays were due to the need to erect scaffolding and remove solar panels.
  • Internal remedial work was completed on 29 January 2024 and it would arrange for decorators to attend once the plaster was dry.
  • It apologised for the delays and had identified points from this case that it could learn from, including the need for better communication with its contractors, improved safety checks, tracking of commitments made and identifying repeated failings earlier.
  • It would offer financial compensation once the resident had sent a breakdown of costs she had incurred. 

April 2024

The resident sent the landlord breakdown of costs for items she had replaced. These included:

  • £120 for carpets and underlay.
  • £20 for curtains.
  • £15 for a rug.
  • £40 for a wardrobe and lamp table.
  • £400 for a bed and mattress.

The landlord agreed to reimburse the resident £595 for the above and pay compensation of £305 for the inconvenience caused by delays.

Referral to the Ombudsman

The resident wants the landlord to reflect on her situation and learn from it. She felt that the landlord only acted once she said she would take her complaint to us. She would also like additional compensation as she said she was unable to use a bedroom for a year while she waited for repairs.  

 

What we found and why

The circumstances of this complaint are well known by the parties involved, so it is not necessary to detail everything that’s happened or comment on all the information we’ve reviewed. We’ve only included the key information that forms the basis of our decision of whether the landlord is responsible for maladministration.

Complaint

The landlord’s handling of roof repairs

Finding

Service failure

  1. On 3 November 2022, the resident reported that the ceiling in her daughter’s bedroom was bowing and full of water. Water was coming in due to damage to the roof. She told the landlord she was terrified the ceiling would collapse. The landlord had no availability to complete a roof repair and passed the job to a contractor.
  2. The next day, the landlord recorded the job as an emergency and noted repairs should be carried out as required to the slate/tiled area of the roof to ensure the area was waterproof. The landlord did not have a repairs policy, but its website says it will attend an emergency repair within 24 hours to make the property safe. There was no evidence the landlord attended within this timeframe. This was unreasonable and likely added to the resident’s distress.
  3. Between November 2022 and October 2023, the landlord raised 11 jobs in relation to the roof repair. However, its records did not show what work was completed for each job. The lack of detail may have contributed to delays in completing repairs and finding a permanent solution to the water ingress. Efficient record keeping and effective systems allow landlords to track the status of repairs, ensuring timely completion.
  4. During this time the resident expressed her worry about the safety of the ceiling on multiple occasions. The landlord noted that she was ‘very concerned’ that the ceiling would collapse.  It would have been reasonable for the landlord to complete a risk assessment of the property to ensure it was safe for the household to use the room. There is no evidence that it did this and this likely led to the resident feeling further distress about the safety of her children.
  5. While the landlord apologised in its stage 1 response for delays and poor communication, the apology did not adequately put things right. It failed to recognise the distress or inconvenience the resident experienced after chasing repairs for 11 months and raising safety concerns. The landlord’s compensation policy says it could offer financial compensation for a ‘major avoidable delay in completing a repair’. It was unreasonable the landlord did not consider any other remedy at this stage.
  6. The roof repairs were completed in November 2023. In its stage 2 response, the landlord apologised for taking a year to finish repairs. It said remedial works would be completed by 14 February 2024 and compensation would be offered once the resident confirmed the costs she incurred due to water damage. This response was reasonable and showed the landlord considered the impact on the resident and took appropriate steps to put things right.
  7. On 12 February 2024, while emailing about compensation, the resident told the landlord that she had to sleep on the sofa for 12 months, which had impacted on her medical conditions, while the repairs were outstanding. The landlord’s compensation policy allows compensation when a resident cannot use a room in their home. It would have been reasonable for it to have considered if the room had been unusable, if any compensation was appropriate and confirm its position to the resident. There was no evidence that it did, which likely caused the resident additional distress as her requests went unanswered.
  8. The remedial works were completed by 13 February 2024. In April 2024, the landlord awarded compensation of £305 for inconvenience and £595 reimbursement for damaged items. This was positive and showed the landlord followed through on commitments it made at stage 2.
  9. However, while the landlord’s offer of £305 compensation showed it considered the inconvenience of the repairs taking over 12 months to complete, it failed to recognise the distress caused and the time and trouble taken by the resident to chase a resolve to the issue during that time.  Its complaints policy says that it can offer compensation for time and trouble, as well for any distress caused. There was no evidence that the landlord considered this as part of its resolution.
  10. Overall, while it was unsatisfactory that roof repairs took 12 months to complete, the landlord identified this and made steps to put it right through the complaints process. However, the steps it took were not proportionate to the impact on the resident and it failed to consider its policies when seeking to resolve the issues and put things right.

Complaint

The handling of the complaint

Finding

Maladministration

  1. The landlord acknowledged the stage 1 complaint after 8 working days. Its complaints policy says it will acknowledge complaints within 5 working days. This meant there was a 3 day delay in the resident receiving her response. The delay was minimal and unlikely to have had a significant impact on the resident. 
  2. The resident requested to escalate her complaint to stage 2 on 5 November 2023. She told the landlord she was not satisfied with its response and not happy that it had not set a date to start works. Internal emails from November 2023 show the landlord decided not to escalate to stage 2. Instead of a stage 2 investigation and response it planned to send an update letter. The landlord’s complaint policy stated that when an escalation is denied, this must be clearly communicated to the resident in writing. The landlord did not show it informed the resident it had refused her escalation request or that it explained why.
  3. The Housing Ombudsman’s Code says landlords must not unreasonably refuse to escalate a complaint through the complaints process. The resident’s request for escalation was fair because the landlord had not confirmed when works would start, which it had said it would prioritise in its stage 1 response. For this reason, the decision not to escalate the complaint was unreasonable and not in line with the Code.
  4. As the landlord had not communicated its decision not to escalate the complaint, the resident continued chasing a response. In January 2024, when the landlord still had not replied, she asked this Service for help, causing her unnecessary time and trouble.
  5. On 29 January 2024, we asked the landlord to provide a response to the resident.  The landlord responded at stage 2 on 1 February 2024. While it was positive that the landlord eventually responded, it should have done so without this Service intervening. In its response, it apologised for the delay in responding but did not offer a full explanation for how the delay occurred which its complaint policy says it will do. The 3 month delay in responding and lack of a full explanation was unreasonable and likely caused further frustration, which the landlord did not acknowledge.
  6. As part of her request to escalate her complaint, the resident said she wanted to be able to access this Service. In most circumstances, residents are only able to ask us to investigate their complaint once they receive a stage 2 response. The landlord’s failure to respond on time delayed the resident’s ability to access this Service if they remained unhappy with the outcome of the landlord’s complaints process.
  7. The landlord’s apology for its delay in escalating the complaint was appropriate. However, its refusal to escalate was unreasonable and its complaint response did not address the impact the delay would have had on the resident.

Learning

  1. The landlord’s complaint responses were well structured with clear subheadings for findings, redress and learning. The layout showed the landlord considered the Dispute Resolution Principles; to be fair, put things right, and learn from outcomes. The presentation of the responses made this clear to residents.
  2. The landlord does not have a repair policy and its website only explains that emergency repairs will be attended within 24 hours. It offers no timescales for urgent or routine repairs. Having a clear repairs policy with defined timescales provides transparency and accountability. It helps residents to understand when issues will be addressed and reduces uncertainty. The landlord is encouraged to consider implementing a repair policy or updating its website with this in mind.

Knowledge information management (record keeping)

  1. The landlord’s repair logs were unclear about what work was completed under each order and simply marked jobs as complete with no further detail.  The landlord is encouraged reflect on how to ensure its records are accurate and detailed. It could review guidance we have published on knowledge and information management and consider any learning.